HomeMy WebLinkAboutRES 1974-009 RESOLUTION N0. ?4-9
RESOLUTION OF AGREEMENT TO CONSTRUCT SEWAGE
INTERCEPTOR MAIN UNDER FEDERAL GRANT
WHEREAS, the City of Grapevine, Texas , has made application to the
�-..
Texas Water Quality Board and the Environmental Protection Agency for a
�' federal grant pursuant to the Federal Water Pollution Control Act Amend-
ments of 1972, Public Law 92-500, and the rules and regulations thereto.
NOW, THEREFORE, BE IT RESOLVED by the City of Grapevine that the
application for which federal grant assistance has been requested pursuant
to the Federal Water Pollution Control Act Amendments of 1972, Public Law
92-5Q0, will be constructed to completion in accordance with the laws,
rules, and regulations and with the following project schedule.
Project Schedule Item Date of Action
General
Availability of Financing Funds
for applicants share of the
�;.� project costs Step 1 October 1 , 1974
Step 2 June l , 1975
��,,.
� Step 3 September 1 , 1975
Availability of Sites
for the project facilities Before advertising for
construction bids
Step 1
Infiltration/Inflow Analysis
Initiated December 1 , 1974�� �
Completed February 10, 1975
Submitted to State (TWQB) February 17, 1975
Preliminary Infiltration/Inflow
Evaluation Survey Study Plan (if needed)
Initiated April 4, 1975�2�
Completed April 14, 1975
�- ,
Report Completed April 21 , 1975
Submitted to State (TWQB) April 28, 1975
� Infiltration/Inflow Evaluation Survey (if needed)
�,.� Initiated May 15, 1975�3�
Completed September 1 , 1975
Report Completed October 1 , 1975
Submitted to State (TWQB) October 8, 1975
Project Schedule Item Date of Action
Schedule, if I/I Schedule, if I/I
Evaluation Survey Evaluation Survey
is not Required is Required
� � Environmental Assessment
Initiated March 17, 1975 November 14, 1976
Completed April 11 , 1975 December 8, 1975
Public Hearing Advertised April 14, 1975 December 10, 1975
Public Hearing Conducted May 15, 1975 January 12, 1976
Environmental Assessment
Finalized June 2, 1975 January 26, 1976
Submitted to State (TWQB) June 2, 1975 January 26, 1976
The Regional Planning Agency
Comments and Approvals Completed June 16, 1975 February 9, 1976
Submitted to State (TWQB) June 16, 1975 February 9, 1976
Facility Plan (Including Final Engineering
Report/Feasibility Report)
Initiated February 10, 1975 September 1 , 1975
Completed March 31 , 1975�2� November 17, 1975
�_.� Report Completed April 4, 1975�2� December 1 , 1975
Public Hearing (30 day minimum period
�• � of Advertisement) May 15, 1975 January 12, 1976
Submitted to State (TWQB) June 16, 1975 February 9, 1976
Step 2
Final Plans and Specifications
Initiated August 4, 1975�4� March 15, 1976
Completed December 1 , 1975 July 18, 1976
Submitted to State (TWQB) December 15, 1975 August 1 , 1976
(1 ) Based on Grant offer by December 1 , 1974.
(2) Based on TWQB and EPA review and comments within 45
days after submittal of infiltration/inflow analysis.
(3) Based on authorization to proceed within 14 days after
�.,,w.;�
submitting survey study plan.
(4) Based on authorization to proceed within 45 days after
submitting Regional Planning Agency approvals.
2.
. • �� '
Project Schedule Item Date of Action
Step 3
Advertise for Construction Bids
within the days indicated after
authorization to advertise for
� bids has been issued 45 days
�
;� Submit Bid Opening Documents
within the days indicated after
the bid opening date 30 days
Award Construction Contract
within the days indicated after
authorization to award the
contract has been issued 15 days
Initiation of Construction
within the days indicated after
initiation of construction 30 days
Complete Construction
within the days indicated after
initiation of construction 270 days
Be it further resolved, that the City of Grapevine understands that
the above project schedule must be approved by the Texas Water Quality Board
and the Environmental Protection Agency, and that once a project schedule
���
has been approved, no changes will be authorized without first receiving
�"'`�'° approval of the change from the Texas Water Quality Board and the Environ-
mental Protection Agency.
Passed, approved and adopted this 3rd day of September ,
1974.
r
f� '_
,�� - , � :��� _��r
W. D. Tate, Mayor
City of Grapevine, Texas
(Seal)
ATTEST:
�,.�
���sast�`� ���.
Kerineth Pritt, Clty Secretary
� City of Grapevine, Texas
3.