From:Don Dixson
Sent:Wednesday, December 9, 2020 3:39 PM
To:Lawrence Gray; Morris Carrejo; James Adams; Connie Cook; Guita McIlroy; Vicki Hecko;
Arnoldo Ramirez; Hans Strayer; Mark Meyers; Scott Leavelle
Subject:FW: [EXTERNAL] vestibule enclosure
Here is the email confirming the erection and removal date. Make a copy and place in the file.
Don Dixson, CBO
Assistant Building Official
Grapevine Development Services
200 S Main St
Grapevine Texas 76051
817-410-3129
817-454-1966
TSBPE – I-2426
RAS – 1425
CEO – 4170
From: Gus Tolleson [
Sent: Wednesday, December 9, 2020 3:33 PM
To: Don Dixson <
Cc: Rick Kessinger <
Subject: FW: [EXTERNAL] vestibule enclosure
*** EXTERNAL EMAIL COMMUNICATION - PLEASE USE CAUTION BEFORE CLICKING LINKS
AND/OR OPENING ATTACHMENTS ***
Good afternoon Don,
If you could please see your email at the bottom of this thread, I have included the answers (highlighted) to the bullet
points you had sent that are required for the installation of the Great Wolf Lodge Vestibule.
This should be everything, per our conversation, that you need to get this project rolling. Let me know if there is
anything else you need from me, but otherwise, I appreciate the help on the phone earlier!
2
Best,
Gus Tolleson
USA Canvas Shoppe
10119 Gardner Road
Dallas, TX 75220
Cell: 469-866-1773 l Office: 972-484-7633 l Fax: 972-620-0364
From: Rick Kessinger
Sent: Friday, December 4, 2020 11:05 AM
To: Keith Furnas
Subject: Re: [EXTERNAL] vestibule enclosure
We just need an install and removal date.
Get Outlook for iOS
From: Rick Kessinger <
Sent: Friday, December 4, 2020 11:04:19 AM
To: Keith Furnas <
Subject: Re: [EXTERNAL] vestibule enclosure
Yes to all the above.
Get Outlook for iOS
From: Keith Furnas <
Sent: Friday, December 4, 2020 11:01:00 AM
To: Rick Kessinger <
Subject: FW: [EXTERNAL] vestibule enclosure
See below. Can you get me the answers?
Keith Furnas | General Manager
Great Wolf Lodge - Grapevine
Grapevine, Texas
Direct: 817-722-3878
From: Don Dixson <
Sent: Friday, December 4, 2020 10:58 AM
To: Keith Furnas <
Subject: RE: [EXTERNAL] vestibule enclosure
Mr. Furnas:
3
I checked the permit historical file for the ‘membrane structure’, and talked with Mr. Stombaugh
relating to a meeting you all had back in October 2020. If you could verify that the membrane
structure is:
1. Being used to aid in climate control
Yes
2. Offering energy savings and
Yes
3. Of a temporary nature by an install and removal date as well as
Yes, installation of the vestibule is to be the week of December 14th, 2020, and the removal of the vestibule is to be
April 15th, 2021
4. Not a permanent addition to the existing building structure
Yes
I do not see why the membrane structure supplied by the manufacturer/representative would need to
comply with the plan review comments letter issued. As, submitted for permit on 11/16/2020, the
impression from the drawings as submitted were that this entry vestibule was of a permanent nature.
The plans indicate a structure; but do not address any material types for the super-structure or façade
materials. Once the temporary structure is documented as such; the contractor may proceed with the
installation of the membrane structure.
Regards,
Don Dixson, CBO
Assistant Building Official
Grapevine Development Services
200 S Main St
Grapevine Texas 76051
817-410-3129
817-454-1966
TSBPE – I-2426
RAS – 1425
CEO – 4170