HomeMy WebLinkAboutItem 03 - Hudgins Street Design MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM. BRUNO RUMBELOW, CITY MANAGER
MEETING DATE: AUGUST 7, 2012
SUBJECT: HUDGINS STREET DESIGN CONTRACT AWARD
RECOMMENDATION:
City Council consider approving an engineering services contract with Pacheco Koch in
an amount of $140,950.00 for engineering design services on the Hudgins Street
Corridor Roadway and Pedestrian Enhancement Project, authorize the City Manager to
execute said contract, and take any necessary action.
FUNDING SOURCE:
Funding for this project is programmed as follows:
Phase I
Quality of Life $ 141,750
GO Bonds* $ 567,000
Phase II
Future Certificates of Obligation $ 793,000
Total $1,501,750
*The Sustainable Development grant funds were reallocated/swapped with the Stone
Myers Roadway Project and approved by NCTCOG and Council to streamline the
construction of this project.
BACKGROUND:
The City submitted the Hudgins Street Corridor Roadway and Pedestrian Improvements
project in the last NCTCOG call for projects. The NCTCOG submittal is comprised of
the corridor segment between Ball Street and Bellaire Drive with additional pedestrian
improvements from Bellaire Drive to Church Street and from Ball Street to the entrance
to Nash Farm.
This NCTCOG project is Phase I of the total Hudgins Street project and is fully funded
by the City after the funding adjustments with the Euless Grapevine/Stone Myers
0:Iagenda12012107-17-121TCAP Contract Memo
August 1,2012(9:36AM)
Parkway project. However, the project still falls under the NCTCOG program and
requires compliance with NCTCOG processes.
Phase II extends from Bellaire Drive to Main Street with a continuation of the roadway
improvements as well as the alignment adjustment at Church Street to align with Ira E.
Woods Avenue. The project includes the potential for additional pedestrian amenities in
the corridor. This increased level of pedestrian amenities' design cost is a separate line
item that can be utilized at the direction of the City Council.
NCTCOG has just recently issued a Notice to Proceed to us that allows us to begin
design of this project.
Staff interviewed two engineering firms with in-house surveying capabilities for this
project and Pacheco Koch was the preferred firm.
Staff recommends approval.
0Aagenda12012107-17-121TCAP Contract Memo