MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: BRUNO RUMBELOW, CITY MANAGER ,A br,_.
MEETING DATE: JUNE 2, 2009
SUBJECT: CONSTRUCTION MANAGER AT RISK FOR THE CONVENTION &
VISITORS BUREAU HEADQUARTERS AND MUSEUM COMPLEX
RECOMMENDATION:
The Convention & Visitors Bureau review committee recommends that the City Council
consider awarding the Construction Manager at Risk contract to Byrne Construction Services
for the Convention & Visitors Bureau Headquarters and Museum Complex. The Pre-
Construction Services and General Conditions Costs are not to exceed $335,910 and the
Construction Services Fee will not exceed 2.95%. See attachment A.
FUNDING SOURCE:
Funds are available from Bonds issued in December 2008 and May 2009 totaling
$11,700,000.
BACKGROUND:
The Construction Manager at Risk process is one where the company that builds the project,
holds the subcontracts and is responsible for guaranteeing the work, its cost and completion
date.
The CM at Risk process also allows the owner to select the most qualified company to deliver
the project when it is needed and at the best price. By instructing that the CM at Risk
competitively bid to subcontractors all of the work except the general conditions and fee, the
owner is assured that they are getting the lowest possible price. In selecting a construction
manager that is skilled, experienced, and works well with architects and engineers, the owner
gains a valuable team member whose efforts and expertise can reduce construction cost and
speed up construction.
A Request for Proposal for the Construction Manager at Risk was created by the Convention
& Visitors Bureau with assistance from Purchasing, Engineering and Risk Management. The
Request for Proposal was published and all bids were opened on Thursday, April 16, 2009 by
Charles Dent, Purchasing Agent. Charles examined all proposals for completeness of pricing
and forwarded the analysis to the review committee.
5/28/2009; 3:44:00 PM
The review committee consisted of members from Engineering, Historic Preservation,
Facilities, Finance and the Convention & Visitors Bureau. These members all provided
valuable expertise within critical areas of constructing the Convention & Visitors Bureau
Headquarters and Museum Complex and five firms were selected to present to the review
committee.
To remain impartial and objective, each firm was to conduct a 30 minute presentation with a
20 minute question and answer period. Each firm received an identical agenda from the
Convention & Visitors Bureau and was given an equal amount of time to prepare for their
presentation. After all presentations were given, the committee members deliberated on
which top two firms were to return for follow-up interviews.
The intention of the interview was to give the firm specific details on the scope of the project,
to establish each firm's qualifications and ideals of the project and to determine which firm
best fit our needs. Upon lengthy discussions by the committee, Byrne Construction Services
was chosen to negotiate the bid at length.
During negotiations, strategies were reached, basic timelines put in place and a fee structure
was established. All critical benchmarks were satisfied and it was resolved to recommend
Byrne Construction Services to the Council.
5/28/2009; 1:13:10 PM
Attachment A
City of Grapevine
Convention Center and Visitors Bureau Headquarters and Museum Complex
General Conditions Cost Breakdown
Description Cost % of Time
Project Manager $99,330 100
Project Engineer $33,000 50
Superintendent $105,780 100
Safety Manager $12,600 20
Field Engineer C.O.W
Field Engineer Helper C.O.W
Licensed Survey $3,248
Safety Program $541
Power for Offices C.O.W
Constuction Utilities C.O.W
Clean-Up C.O.W
Office Supplies $5,413
First Aid/OSHA Supplies/AED $1,624
Fire Ext. Setup& Recharge $974
Printing Record, Shop Drawings(misc) $2,400
Progress Photos C.O.W
Delivery Services $1,353
Temporary Toilets C.O.W
Dumpster&Trash Dumping Fees C.O.W
Telephone&Fax $10,122
Small Tools C.O.W
Jobsite Truck(s)/Automobile(s) $20,026
Office Trailer $12,449
Job Sign $866
Equipment/Hoisting C.O.W
Perimeter(Temporary Fencing) C.O.W
Safety Rails C.O.W
Copy Machine $4,871
Postal Scales $1,353
Computer C.O.W
Tool&Storage Sheds $1,840
Gas, Oil, Grease, equipment repair $12,990
Mobile Phones $4,330
Drug Testing $800
Payment&Performance Bond C.O.W
General Liability/Umbrella C.O.W
Builder's Risk C.O.W
Total: $335,910
BYRIE
Thos . S. Byrne Proposal
•
GCVB-001-Construction Manager at Risk
Revised May 22, 2009
Attachment"F"
City of Grapevine, Texas
Pre-Construction Services Price Proposal
Provide a Fixed Price on a monthly basis base on your Proposed Pre-Construction Services as
specified in Attachment"D",Construction Management at Risk Contract,developed to support the
dates listed in this RFP. Attach an hourly rate schedule indicating rates for each individual
shown on the Organizatonal Chart provided in your response to RFP Section 2.5.1.1
Pre-Construction Services,monthly work hours proposed for each,and detailed listing of
Reimbursable Expenses in conformance with allowables listed in Page 2 of this Attachment.
F1.1 Fully Loaded Monthly Rate $ Scope
Total Personnel Rate for 6 Months $12, 000 $
Averge Rate/Month for 6 Months $2, 000 $12, 0 0 0
F1.2 Reimbursable Expenses $
Printing l 1 nwancP) $7. 000
Not To Exceed*Total Reimbursables for 6 Months $7, 000
$
Average Rate/Month for 6 Months $1, 167 _ $7, 000
* Monthly billings supported by receipts
F1.3 Markup for On-Site Services No Charge 0%
F1.4 APPROXIMATE TOTAL MONTHLY R"TE FOR PRE-CONST.SERVICES. $19, 000
Lump Sum
Thos. S. Byrne Proposal
GCVB-001 -Construction Manager at Risk Revised May 22, 2 0 0 9
Attachment"G"
City of Grapevine, Texas
Construction Services Price Proposal
G1.1 Construction Phase Services
G1.1.1 General Conditions
Provide a proposal for the cost of General Conditions as a percentage of total"Direct $335, 910
Costs"as defined in Attachment"D"Construction Management at Risk Contract,
excluding only the costs compensated under Fee, Insurance, and Bonds. See Attached N/A %
G1.1.2 Fee for Construction Services
Fee for Construction services as a percentage of the total"Direct Costs,"excluding
General Conditions costs, and to include CMAR's onsite labor costs. Fee percentage
should be inclusive of all overhead, profit, insurances, general requirements, etc.
(office personnel and overhead) not included in the General Conditions. 2 . 95 %
G1.1.3 Costs of Insurance - See itemization below . 5 %
G1.1.4 Costs of Bonds - Based on $8 .5 Million . 8 %
G1.1.5 Additional Costs
If there are costs for which reimbursement is expected explain these in detail in an
Appendix to this Attachment. 0 %
G1.1.6 , TOTAL MARKUP APPLIED TO DIRECT COSTS 7. 98%
Oak
G2.1 Dead Band
Owner changes to the original construction scope shall not necessitate additional Fee
unless the changes cause additional personnel to the CMAR's staff, or extend the
General Conditions. Accordingly, provide the cumulative percentage of additive
changes which are acceptable without an increased Fee, and a percentage markup
applicable to changes in excess of that amount as follows:
Dead Band 1.5 %
Changes in Excess of Dead Band 2. 95%
Example:
For a Project with$ Million to$ Million range,the Construction Services Fee is:
General Conditions as defined above 5%
Fee as defined above 3%
Insurance 0.75%
Bonds 0.75%
Additional Costs 0%
Total Markup as defined above 9.50%
Assume a 10% Dead Band with a 2% Fee over Dead Band and the City makes changes that cost 15%over
Direct Costs for the original Project Scope. Therefore,the first 10% in City changes would incur no additional
Fee, but the 5% in excess of the Dead Band would be subject to the 2% Fee. Additional General Conditions
would be negotiated on a case-by-case basis to the extent applicable based on extensions to the Project ,,,
Schedule.
General Liability - .230
Umbrella - . 15%
Builder' s Risk - . 12%