HomeMy WebLinkAboutItem 05 - Palace Theatre Change Order #14;0"
ITEM +I
TO: HONORABLE MAYOR AND CITY COUNCIL MEMBERS
FROM: ROGER NELSON, CITY MANAGER F"
MEETING DATE: MAY 2, 2000
SUBJECT: PALACE THEATRE CHANGE ORDER #1
RECOMMENDATION:
Staff recommends the City Council approve change orders for the Palace Theatre totaling
$71,536 and take any other necessary action.
FUNDING SOURCE:
Funds are available in the following accounts.
Account 816-48840-101-01, Palace Theatre Construction $4,895,572
BACKGROUND INFORMATION:
The Palace Theatre Reconstruction Project has a projected budget of $4,895,572.00. Due
to the extensive reconstruction of the project and unknown factors of the original
construction, the budget included a substantial contingency of $402,118.00 for the
reconstruction of the Palace Theatre. In the past few weeks the architects, engineers and
construction manager had begun the reconstruction of the structural elements of the
building and have discovered several areas that must be addressed to assure that we have
a safe building when the reconstruction is complete.
The proposed change orders represent areas of structural alterations throughout the
Palace Theatre, the Lancaster Heritage Theatre, as well as the area know as the Ski Shop.
The Ski Shop requires substantial work on the existing brick arch as well as removal of one
brick wall that is structurally unsound.
Staff has previously approved six change orders. These change orders were for three
different contracts and none of the change orders increased the net amount of the
respective contract more than $15,000. State law allows staff level approval of change
orders under this amount. The previously approved change orders are as follows:
CHANGEORDERSI 1 April 27, 2000 (10:08AM)
PREVIOULY APPROVED CHANGE ORDERS
PHASE 1 - SITE DEMOLITION
Contractor & Contract Number Description
Midwest Wrecking GHF - 01 Tower & I -Beams
Midwest Wrecking GHF - 01 Roof/Concrete
Removal
TOTAL, PREVIOUSLY APPROVED CHANGE ORDERS
DIVISION / DEMOLITION
Contractor & Contract Number
Midwest Wrecking GHF-01A
Midwest Wrecking GHF-01A
Midwest Wrecking GHF - 01A
TOTAL NET CHANGE ORDER
DIVISION 15 MECHANICAL
Contractor & Contract Number
Ivey Mechanical GHF - 16
TOTAL NET CHANGE ORDER
Description
Temp Shore; Pavers
Sawcut, Remove
Electric Trench
Pavers, Sawcut
Remove Etc.
Description
Move Condensing
Unit
Amount
$(5,142.07)
$12,256.72
Amount
$ 5,649.90
$ 987.46
$ 1,650.94
Amount
$ 551.97
�1tell f_1Kole] Ly, 1-]1►1:13ZN:ElZcc] moo]:]Q4 S&11: EIPYA
The following is a brief description of why this Change Order in the amount of $71,536 is
being requested:
1) Repair of the brick arch in the Ski Shop. The existing arch in the Ski Shop has many
cracks in the mortar. The engineer has issued instructions that the wall should be
repointed to maintain its integrity.
2) Repair of north wall of Heritage. The existing block wall on the Palace side was
unsupported on the Heritage side because a wythe of brick was missing. Structural
engineer reviewed and advised that the brick should be filled in up to the bottom of
the block on the Heritage side. Additionally, a steel angle was specified to be
installed to reinforce the joining of the two dissimilar materials.
CHANGEORDERSI 2 April 27, 2000 (10:08AM)
3) Modification of stair well and wall between Palace and Heritage. A door at the front
of the Palace near the stage on the south wall was always planned to join the two
theaters together. However, after removal of the rear wall it was determined that
the door opening was too close to the end of the wall to cut the opening due to the
deterioration of the wall. The structural engineer advised that we should remove the
last eight feet of wall full height, pour a new foundation, and construct a new wall.
Additionally, this change involved strengthening the pit on the Heritage side to
support the new construction.
4) Removal of a portion of the north rear Ski shop wall and reconstruction with brick,
cmu, and clay tile. Unfortunately, the existing north wall to the west of the arch
between the Ski Shop and Heritage was not well constructed and could not be
saved. Not only is this a structural wall that supports the wood trusses, but our plan
called for an additional five feet of masonry construction to be built on top of the
existing wall. There was no practical way to achieve this goal. The engineers'
instructions are to remove the wall and replace with three wythes of brick, cmu, and
structural clay tile. This wall is to be built on a new concrete foundation which
consist of a new 36" pier, cantilevered pier cap, and grade beam. In the effort to
maintain as much of the existing structure, we are shoring the existing wood trusses
and roof while construction is done so that it does not have to be removed.
5) Revised support of the air conditioning units over the Ski Shop. This change is
similar to the one above in that the engineer decided that it was not a good plan to
bear the weight of the new roof -top air conditioning units on the wall of the Ski
Shop. His plan is to support the steel I-beam supports by pipe columns located in
the space below that bear on a gradebeam running perpendicular in the building.
6) Modification of ramp and stairs at front between Palace and Heritage. This change
does not involve extra money, but adds detail to the construction and relocates
slightly the ramp and stair that link the Palace and Heritage at the front.
7) Support of third floor cantiliered beam in the Palace. This change involves
supporting a concrete beam that exists in the Palace at the third floor. The plans
call for removal of a portion of the wall beneath and its connection to the front wall.
In order to give added support, the engineer devised beams and hangers to
support the end of the beam.
8) Columns under beam at mezzanine. Instead of bearing the new I-beam at the
Palace mezzanine into a masonry pocket in the wall, the engineer has instructed us
to install columns at each end and bear the columns on a small footing.
9) I -beams around perimeter of Palace for deck support. After excavation of the
foundation, it was discovered that it was different that what was anticipated, and
CHANGEORDERS1 3 April 27, 2000 (10:08AM)
potentially would not provide adequate support for the new concrete deck.
Therefore, the structural engineer revised the plan to call for additional I -beams to
be placed under the deck and welded to the already planned columns to transfer
the load to the columns instead of the wall. Also, a slip joint connection was used
to allow for slippage in the event the walls moved differently than the deck.
10) Pier cap in lobby due to relocated column. A column was relocated in the lobby to
ensure good egress to the cafe.
11) Temporary piers and shoring. This is a recommendation to help support the walls
of the Palace during construction since no rear wall exists and heavy work is
planned to take place around the building.
12) Modifications of elevator pit. The elevator pit was modified to provide a more
suitable foundation than the original design as well as increase in size.
The Change Orders to be approved are as follows:
DIVISION / DEMOLITION
Contractor & Contract Number Description Amount
Previously Approved Change Orders $ 8,288.30
Midwest Wrecking GHF - 01A Modification of Pit $ 4,670.00
Midwest Wrecking GHF - 01A Ski Shop North Wall $ 2,800.00
TOTAL NET CHANGE ORDER (for approval) ,
Total Midwest Change Orders (Previous + Present) $15,758.30
DIVISION 2/3 CONCRETE
Contractor & Contract Number Description Amount
Jaz Concrete Inc. GHF - 04
Modification of Pit
$
3,489.00
Jaz Concrete Inc. GHF - 04
Ski Shop North Wall
$
5,207.00
Jaz Concrete Inc. GHF - 04
Ski Shop A/C Support
$
2,796.00
Jaz Concrete Inc. GHF - 04
Pier Cap in
Palace Lobby
$
1,678.00
Jaz Concrete Inc. GHF - 04
Temp. Piers and Shoring
$
1,550.00
Jaz Concrete Inc. GHF - 04
Elevator Pit Modification
$ 2,193.00
TOTAL NET CHANGE ORDER
1$16,193.Oq
DIVISION 4 MASONRY
Contractor & Contract Number
Description
Amount
C&D Com. Masonry GHF - 05
Repair Brick Arch
$
908.00
CHANGEORDERSI
4
April 27, 2000 (10:08AM)
C&D Com. Masonry GHF - 05 Repair North Wall
of Heritage $11,252.00
C&D Com. Masonry GHF - 05 Modification of Pit $ 3,631.00
C&D Com. Masonry GHF - 05 Ski Shop North Wall $18,360.00
TOTAL NET CHANGE ORDER
DIVISION 5 STRUCTURAL STEEL
Contractor & Contract Number Description
H&H Steel Fab.
GHF - 06
Repair North Wall
of Heritage
H&H Steel Fab.
GHF - 06
Ski Shop A/C Support
H&H Steel Fab.
GHF - 06
Cantilevered Concrete
Beam Support
H&H Steel Fab.
GHF - 06
Column Under
Front Balcony
H&H Steel Fab.
GHF - 06
Beam Under Deck in
Palace at Wall
TOTAL NET CHANGE ORDER
Amount
$ 600.00
$ 8,718.00
$ 379.00
$ 229.00
. 0�
I to] "►1,1:10,114 : /_1. [h ��'% ill- , I I
HTH/sdk
CHANGEORDERS1 5 April 27, 2000 (10:08AM)