MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: ROGER NELSON, CITY MANAGER
MEETING DATE: JUNE 6, 2000
SUBJECT: FIRST PHASE / PUBLIC IMPROVEMENTS - OPRYLAND
RECOMMENDATION:
City Council consider rejecting all bids for construction of Gaylord Trail Improvements,
the First Phase of Public Improvements under the Opryland TIF, authorize staff to re-
advertise said project, and take any necessary action.
FUNDING SOURCE:
Funds are currently available in Account # 173-72115-0001
"Notice of intention to issue City of Grapevine, Texas Combination Tax and Tax
cay Increment Reinvestment Zone Revenue Certificates of Obligation, Series 2000"
BACKGROUND:
The First Phase of Public Improvements consists of the main entrance road into the site
from State Highway 26, the 500 foot bridge over the Silverlake branch of Lake
Grapevine, intersection improvements and traffic signals at SH 26, the main water trunk
line serving the hotel site, ROW irrigation and landscaping. This particular package
needs to be in place before the Supplemental Public Improvements package is begun.
The Supplemental Public Improvements package will include improving Ruth Wall from
Northwest Highway to the hotel site, a box culvert and raised roadway through the low
area north of Wildwood Drive, the Opryland lift-station, force-main and Trencor trunk
line, and the continuation of the hotel site water trunk line. This project is anticipated to
begin in late 2000 or early 2001, based upon the progress of the First Phase Project.
The engineer's estimate for this First Phase package is $ 5,983,694.
June 1, 2000 (1:18PM)
Bids were opened on Thursday, May 04, 2000 at 2:00 pm. Three bids were received as
follows:
Base Bid Alternate Bid
Archer Western $ 5,317,225.25 $ 5,293,415.61
J. D. Abrams $ 7,131 ,613.20 $ 7,064,031 .34
Rebcon $ 7,388,697.50 $ 7,332,581 .50
Archer Western advised us in writing shortly after the bid openings of a $ 1 ,000,000
shortfall error in their bid.
Carter Burgess has reviewed the bid prices and has recommended to Gaylord staff and
City staff that the project be re-bid.
Staff recommends approval.
JSL/dsm
411,
O:\agenda\060600\l stphase.public.imprv.oprylandR
June 1, 2000 (1:18PM)
JUN 81 '00 10:18 FR OPRYLAND HOSP GROUP 615 316 6898 TO 918174103003 P.01/01
GAYLORD ENTERTAINMENT .0101
June 1,2000
Mr.Jerry Hodge
Director of Public Works
Grapevine Texas
200 South Main Street
Grapevine,TX 76051
RE: TIF Package 1 Bids
Dear Jerry:
Please be advised that Opryland Hospitality Group request that the City of Grapevine reject all
bids from the May 4, 2000 bid for the Gaylord Trail TIF Package. It is our intent to re-advertise
for re-bidding this package on June 11 and June 18, 2000.
Should you have any questions concerning this matter please contact me at your convenience.
Sincerel :
Jo '.Edwards
ector of Construction
CC: Dave Jones OHG
Glenn Malone OHG
Rick Charles OHG
Pete Cesari OHG
Mike Cordiner HDC
Chuck Jackson HDC
ONE GAYLORD DRIVE `141)
NAsHv11,LE,TENNESSEE 37214
T,c IHONH6I5-316-6800
FAcsI mi 1 F.615-316-6898
** TOTAL PAGE.01 **