MEMO TO: HONORABLE MAYOR AND MEMBERSOFTHE CITY COUNCIL
F {
FROM: ROGER NELSON, CITY MANAGER
MEETING DATE: JULY 18, 2000
SUBJECT: AWARD OF CONSTRUCTION CONTRACT — PARR PARK
RESTROOM FACILITY
RECOMMENDATION:
City Council to consider awarding a construction contract to Keck and Company for the
Parr Park Restroom Facility improvements in the amount of $ 125,235.00, authorizing
staff to execute said contract, and appropriating $ 34,283.82 of Southwest Grapevine
Area Open Space Fees for the construction of said project and take any necessary
action.
FUNDING SOURCE:
BUDGET
Planning/Design $ 19,365.00 11.6%
Construction 125,235.00 75.4%
Owner Direct Expenses 9,000.00 5.4%
Contingency 12,683.50 7.6%
TOTAL $ 166,283.50 100.0%
SW Open Space Fees $ 34,283.82 Acct. No. 171 -11101 -000 -SW
Parr Park 132,000.00 Acct. No. 176-76113-001
TOTAL $ 166,283.82
July 12, 2000 (10:26AM)
BACKGROUND:
On March 7, 2000, City Council approved a Design Services Contract with Halff and
Assocites, Inc. for the Parr Park Restroom Facility Improvement Project.
On June 27, 2000, two bids were received for the construction of the Parr Park
Restroom Facility. The base bids were as follows:
Keck and Company $ 125,523
T. W. Foster, Inc. $ 220,810
One of the two base bids received was less than the Architect's Opinion of Probable
Cost of $ 158,830. f
Staff thoroughly researched the project history and financial conditions of Keck and
Company. Staff also visited with owners' representatives of numerous completed
projects and found they were satisfied, which further indicates that the low bid of Keck
and Company should be accepted.
Construction time for this project is 140 days.
Staff recommends approval.