HomeMy WebLinkAboutItem 05 - Parr Road ConstructionMEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: ROGER NELSON, CITY MANAGER
MEETING DATE: JULY 31, 2000
SUBJECT: PURCHASE OF RIGHT-OF-WAY FOR PARR ROAD
CONSTRUCTION — PARCEL E, DENNIS SWEEBE
RECOMMENDATION:
City Council consider authorizing the purchase of 9,420 square feet for right-of-way and
the improvements located within the right-of-way for the Parr Road construction project
from Dennis Sweebe in the amount of $6,925.00, authorize staff to execute the
purchase documents, and take any necessary action.
FUNDING SOURCE:
Funds are currently available as follows:
Funding Source
Amount
Account Number
FY1999 GO Bonds
$ 458,665
178-78101-010
FY2000 GO Bonds
$ 2,674,069
178-78102-011
Future Utility Bonds
$ 277,043
Peripheral Street Fees
$ 172,740
TOTAL
$ 3,582,517
Budget
Amount
Percent Expense
Design
$ 278,000
7.8%
Construction
$ 2,390,743
66.7%
Testing
$ 39,100
1.1%
ROW
$ 218,600
6.1% FY99 GO Bonds
Contingency
$ 656,074
18.3%
TOTAL
$ 3,582,517
100.0%
BACKGROUND:
The City Council has previously authorized staff to offer the appraised value of
$ 5,925.00 for the tract. This includes the cost of the right-of-way ( $3,675.00) and an
estimated cost ($2,250.00) for the relocation of the fence by the owner after the project
is complete.
July 27, 2000 (10:OOAM)
The owners relocation of the fence will eliminate the City's contractor relocating the
fence as part of the roadway project.
The owner has responded with an offer of $ 6,925.00 based upon his estimate for the
fence relocation of $ 3,250. 00. Staff feels the request of the owner totaling $ 6,925.00
is reasonable.
Staff recommends approval.