MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: ROGER NELSON, CITY MANAGERe/
MEETING DATE: JANUARY 4, 2000
SUBJECT: DOVE ROAD EXTENSION PAVING AND DRAINAGE
IMPROVEMENT PROJECT IN CONJUNCTION WITH THE
DEVELOPMENT OF WILDWOOD CREEK APARTMENTS
RECOMMENDATION:
City Council consider awarding a Construction Contract for Paving and Drainage
Improvements in Dove Road Extension to J. L. Bertram Construction and Engineering, Inc.,
in the amount of $607,068.11, authorize staff to execute said contract, and take any
necessary action.
FUNDING SOURCE:
Funds for City and Developer participation are currently programmed as follows:
PROJECT FUNDING:
G.O. BONDS Pool Road $ 220,548.97
Developer Participation 437,065.95
Utility Bonds 20.160.00
TOTAL $ 677,774.92
PROJECT BUDGET:
Construction $ 607,068.11
Testing 10,000.00
Contingency (10%) 60.706.81
TOTAL $ 677,774.92
BACKGROUND INFORMATION:
The Wildwood Creek Apartments site was platted in August of 1999 by Fairfield Wildwood
Creek Limited Partnership. At that time, City Staff informed the developer that the
improvements to Dove Road Extension were to be constructed with the development of this
December 28, 1999 8:53AM
site. The plat dedicated the necessary right-of-way for this street between Boyd Drive and
Ruth Wall Street.
Dove Road Extension west of this property is currently a four -lane divided roadway. The
street is designated as a Type "B" Arterial on the Master Thoroughfare Plan (four -lane
divided street within an 80' right-of-way).
Nine bids were received on December 6, 1999. The bid results follow:
J.L. Bertram $607,068.11
Sutton & Associates $653,312.25
Austin $656,110.05
Tiseo Paving $657,631.35
BCI Utility $696,905.75
JRJ Paving $686,515.57
McMahon Contract $696,037.00
Apac-Texas $719,722.40
Ed Wilson $737,560.60
A review of the bids reveal that the bid of the apparent low bidder is in order. J.L. Bertram
has performed various projects in the City over the years with the Pool Road project being
the most recent.
The schedule for the project establishes 90 calendar days beginning 10 days after the
contractor receives a 'Notice to Proceed' from the City. City staff estimates that construction
will begin late January with a completion date of April / May 2000, weather permitting.
Staff recommends approval.
SAD/JLH
oAAGENDA\12-21-99\peachbid.doc
December 28, 1999 8:53AM
GENERAL GOVERNMENT CAPITAL PROJECTS
Dove Road Extension
PROJECT DESCRIPTION
Construction of Dove Road from Boyd Drive to Ruth Wall Street. This roadway will be a four -lane divided street within an
80 foot right-of-way.
PROJECT SCHEDULE Begin End
Design Private Private
Construction Jan -00 May -00
FISCAL IMPACT
Construction 617,068 617,068
Contingency 60,707 60,707
TOTAL: $0 $677,775 $0 $0 $0 $0 $677,775
1996 GO Bonds 220,549 220,549
Developer
Participation 437,066 437,066
Utility Bonds 20,160 20,160
TOTAL: $0 $677,775 $0 $0 $0 $0 $677,775
IMPACT ON OPERATING BUDGET
Operating budget impact includes the cost of periodic street sweeping, maintenance of road markings, sealing of joints in
pavement, and maintaining medians and parkways on both sides of the roadway.
Personnel Expenses 0
Supplies 0
Maintenance 646 1,939 3,395 6,419 6,419 18,819
Services 0
Capital Outlay 0
T«taI- -$6,419 -$6,419 18,819'