MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: ROGER NELSON, CITY MANAGER
MEETING DATE: APRIL 18, 2000
SUBJECT: AWARD OF CONSTRUCTION CONTRACT — GRAPEVINE
PUBLIC LIBRARY
RECOMMENDATION:
City Council consider awarding to T. W. Foster, Inc. a construction contract for the
Grapevine Public Library improvements in the amount of $4,624,54.7 and approving
Change Order No. 1 (which funds the four alternates bid on the project) in the amount of
$160,000, authorizing staff to execute said contract and change order, and appropriating
$170,675 of unallocated 99 and 00 GO Bond Interest and take any necessary action.
FUNDING SOURCE:
BUDGET
Planning/Design $ 615,000.00 8.9%
Construction 4,784,547.00 69.0%
Owner Direct Expenses 613,000.00 8.8%
Furnishings and Signage 650,000.00 9.4%
Contingency 273,030.35 3.9%
TOTAL $ 6,935,577.35 100.0%
Library Building Account $ 14,750.35 Acct. No. 100-48840-313-1
99 GO Bonds 1,000,152.00 Acct. No. 177-48840-010-313
00 GO Bonds 2,875,000.00
01 GO Bonds 2,875,000.00
Unallocated GO Bond Int. 67,000.00
Future GO Bond Int. 103,675.00
TOTAL $ 6,935,577.35
April 13, 2000 (8:39AM)
The future GO Bond Interest amount of $103,675.00 represents interest earned from the
sale and subsequent investment of the GO Bonds during the life of the library
construction project.
On December 5, 1998, the citizens of Grapevine approved Proposition No. 2 which
allowed for the sale of General Obligation Bonds for the expansion and renovation of the
Grapevine Public Library. The existing library facility contains approximately 15,000
square feet. The 38,950 square foot expansion will bring the new library facility to a total
area of 53,950 square feet. The architectural firm of Phillips Swager Associates (PSA)
was selected to design the expansion and renovation of the Grapevine Public Library
project.
On March 21, 2000, nine bids were received for the construction of the Grapevine Public
Library. The base bids were as follows:
T. W. Foster, Inc.
$ 4,624,547
ML & Associates
4,635,000
CMPA, Inc.
4,774,000
G Ratcliff Construction
4,835,911
Frymire Company
4,860,000
R.C. Small & Associates
5,023,000
Hisaw & Associates
5,093,000
Webb General Contractors
5,227,000
Adolfson & Peterson, Inc.
5,407,000
Two of the nine base bids received were less than the Architect's Opinion of Probable
Cost of $4,705,317.
In addition to the base bid, bids for four alternates were also required as part of the bid
package. Alternate No. 1 calls for the provision of Capual "Tuf Core" Acoustical Ceiling
Tile. This is a heavier duty acoustical ceiling the specifically designed for noise
reduction. The cost for this alternate is $18,864.
Alternate No. 2 calls for the provision of an Acoustical Window System which is another
noise reduction feature. This item calls for the removal of the existing perimeter
aluminum window system and glazing. The cost for this item is $134,881.
Alternate No. 3 calls for the construction of a second masonry monument sign at the
east entrance of the library parking area. The base bid includes the construction of a
April 13, 2000 (8:39AM)
masonry monument sign at the entrance to the library from Municipal Way. The cost for
this item is $5,460.
Alternate No. 4 calls for the provision of a "Young Adult" neon sign. The cost for this
item is $795.
Alternates 1 and 2 provide noise mitigation for the proposed DFW International Airport
west runway. Staff recommends the award of all four alternates. The four alternates
comprise Change Order No. 1.
Staff and representatives of the PSA have thoroughly researched the project history and
financial conditions of T.W. Foster, Inc. Staff has visited several ongoing projects of the
contractors which include American Airlines Projects and GCISID projects. Staff has also
visited with owners' representatives of numerous completed projects and has not found
anything which indicates that the low bid of T.W. Foster, Inc, should be rejected.
Attached, please find a letter from PSA dated April 7, 2000 regarding the award of the
contract to T.W. Foster.
Construction time for this project is 390 days.
Staff recommends approval.
RHP\JLH
April 13, 2000 (10:06AM)
rmmTWAW_.', PSA DALLAS
` Mr. Robert Price
Director of Internal Services
City of Grapevine, .
P,p, Box 95104
Grape*vine, Term$ 76099
9'e: Qrapevine Public Libray
Qrapevine;Texas 76051
PSA project No, 41.95 00
Dear Bob
X10.041 P. 2/9
Phillips Swager Associates
On March 21,2000, at 2,00 pm, the bids for the new Grapevite Public 1.ibmy Frere publicly opened an4 read,
The attached bid tabulation ==wrizes the nine bids that were received. The bids Ore co4*cd of'the base bid
and the four 444 alternates,
Based on the base bid, the low bid of $4,624,547.00 was received from T, W . Faster, lap, The second low base
bid of $4,635,000.00 and the Third low base bid of $4,774,000.00 Were received from ML & Associates and
OMPA, Inc:, respectively.. The difference between the first and third lowest bidders is 91149,453.00. This is
approximately a 3.1 % difference and ir1'dicates a close bid.
We have reviewed the references of T,W Poster Inc,, and both owners aad architegts were generally very
positive. They st=d ti c T.W Vos;;er is a corrtpeteut, ditigeut and haiiea Cautractvr , and would not 4= tats
to work with theme again. Wd have an4ched these, comments ;For your reyri.eW, Any 9e4ff4tive continents tended to
focus on conditions specific to a particular •prgject such as iiaeMcieryt Field Supervi$ion, (please refer t4
Referetce No.6 UL Architects) or the Contractor falling behind on the project Schedule during construction, .
although the project was completed an time,(please refer to `Reference No.3, HH Architects, Inc),
We are currently working with MMI,, Associates on two projects, the City of Highland Village Municipal Complex
and Ortbofm New Office and Manufacturing Facility. They have. provided con$pruction services to our clients ,
in a timely and prof6s5iqnal manni r and we have developed a strong wpr" relationship with theta over the
last two years, Our experience whet ML Associates is extremely positive and we will be disappointed when the
two projects come to a close. '
Since the overall response is favo "cable, PhMips Swager Asociates has no objections to you awarding the contract
for the exp=sion of the Grapevirie Public Library to either T,W: Foster, Inc. or ML Associates.
PIP -ase do not hesit4te to call if'you hove any questions regarding this matter.
Sincerely,,
P $ WAGI?R A5S.QC1AT:FS
Dirk M. Dalhausser, AIA
Senior Associate
A4achment
XA4195=0nlS rotor leper of Rec 4 7 OO.wpd
7957 R1mMo+' RU:)d, 4uitr 070
• � ��11:).,'1'x ;5'37-:,.yU2
A)'Cltitec,CS (214) 699-nu3
Eri�t)leer t tl•1) 6v4 -a1 ip Fax
Pjmalers olticos in i1Cv,rla, ('11w.1go,
111inuls'd: Washingion, D.C,
Received Apr -07-2000 08:34pm From -214 882 8118 To -CITY OF GRAPEVINE Pane 002
Vis. ... �.a=
GENERAL GOVERNMENT CAPITAL PROJECTS
Library Expansion
PROJECT DESCRIPTION
Renovation of the existing 15,000 square foot Library facility with a 37,950 square foot addition. The finished
Library will be 52,950 square feet. This expansion will provide for a larger Children's and Youth areas,
expanded Genealogy section, larger collection of books and audio/video materials, expanded programming
space, more computer and study areas, and more patron parking.
PROJECT SCHEDULE Be in End
Planning Oct -98 May -99
Design May -99 May -00
Construction Jun -00 Sep -01
FISCAL IMPACT
IMPACT ON OPERATING BUDGET
Operating budget impact includes additional full- and part-time staffing, additional supplies and equipment,
routine cleaning of the facility with the possibility of part-time day porter service, new plants throughout the
facility, plant maintenance, pest control services, utilities, and general maintenance costs.
Projected Annual
Oper6tin Impact
FY -99 ! FY -00 lFy-ot FY -02
Budget t Planned - Planned Planned
FY -03
Planned
Totats
Tota!
Project
LTD 1
Budget
Planned
Project
Expenses
09/30/98
FY=00
FY -01 FY -02 FY -03 FY -04
Cost .
Planning
14,750
0
110,9101
219,920
Capital Outla
41,500
14,750
Design
79,724
450,000
70,276
$7110;544
600,000
Construction
350,000
4,434,547
4,784,547
Owner Direct
Expenses
25,000
588,000
613,000
Furnishings &
Signage
650,000
650,000
Contingency
50,000
223,280
273,280
TOTAL:
$94,474
$875,000
$5,966,103
$0
$0
$0
$6,935,577
Funding
Source
14,750
0
14,750
General Fund
1999 GO Bonds
79,724
875,000
45,428
1,000,152
2000 GO Bonds
2,875,000
2,875,000
2001 GO Bonds
2,875,000
2,875,000
Unallocated GO
Bond Interest
67,000
67,000
Future GO Bond
Interest
103,675
103,675
TOTAL:
i $94,474
$875,000
$5,966,103
$0
$0
1 $0
$6,935,577
IMPACT ON OPERATING BUDGET
Operating budget impact includes additional full- and part-time staffing, additional supplies and equipment,
routine cleaning of the facility with the possibility of part-time day porter service, new plants throughout the
facility, plant maintenance, pest control services, utilities, and general maintenance costs.
Projected Annual
Oper6tin Impact
FY -99 ! FY -00 lFy-ot FY -02
Budget t Planned - Planned Planned
FY -03
Planned
Totats
Personnel Expenses
92,400
109,500
201,900
Supplies
77,200
29,200
106,400
Maintenance
30,662
32,662
63,324
Services
I I 1 1 109,0101
110,9101
219,920
Capital Outla
41,500
83,5001
125,000
Total
1 $0 $0 $0 $3! tgJ772
$36W721
$7110;544