MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: ROGER NELSON, CITY MANAGER
MEETING DATE: MARCH 6, 2001
SUBJECT: GRAPEVINE PUBLIC LIBRARY — CHANGE ORDERS NO. 4 AND 5
RECOMMENDATION:
City Council consider approving Change Orders No. 4 and 5 to the Grapevine Public Library
Expansion Project with T. W. Foster, Inc., Contractors in the amount of $ 10,877.89 and
$23,476.60, respectively, authorize staff to execute said Change Orders, and take any
necessary action.
BUDGET
Amount
Award
Percent
Library Building Account
Planning/Design
$ 613,805.59
100-48840-313-1
8.8%
Construction
4,832,487.00
177-48840-010-313
69.6%
Owner Direct Expenses
675,000.00
7,381.51
9.7%
Furnishings and Signage
650,000.00
177-48840-012-313
9.4%
Contingency
171.326.65
26.972.98
2.5%
TOTAL
$ 6,942,619.24
$ 34,354.49
100.0%
FUNDING SOURCE:
BACKGROUND:
The Contract for the construction of the Grapevine Public Library improvements was
awarded to T.W. Foster, Inc. Contractors, Inc. by the City Council on April 18, 2000. The
March 1, 2001 (12:12PM)
Amount
Award Percent
Acct. Nos.
Library Building Account
$ 14,750.35
0.21%
100-48840-313-1
99 GO Bonds
1,000,152.00
14.40%
177-48840-010-313
00 GO Bonds
2,879,893.89
41.50%
177-48840-011-313
00-A GO Bonds
2,875,000.00
34,354.49 41.40%
177-48840-012-313
99 GO Bond Int.
67,000.00
0.96%
177-48840-010-313
00 -GO Bond Int.
103,675.00
1.50%
177-48840-011-313
Contractor Reimbursement
2,148.00
0.03°
177-48840-010-313
TOTAL
$ 6,942,619.24
$ 34,354.49 100.00%
BACKGROUND:
The Contract for the construction of the Grapevine Public Library improvements was
awarded to T.W. Foster, Inc. Contractors, Inc. by the City Council on April 18, 2000. The
March 1, 2001 (12:12PM)
Notice to Proceed for the project was issued on May 30, 2000. The original time allotted for
the contract is 390 days.
The construction of Phase I (the new addition) should be completed in mid to late April.
Change Order No. 4 specifically includes one item.
■ Item A is for the furnishing of materials and labor to install additional depth of concrete
piers required to be extended into the bearing stratum deep below the ground surface.
Based upon geotechnical corings, the bearing stratum was estimated to be located
approximately 24' deep. Based upon this study, the bid depth of the 131 foundation piers
was established at 24 feet. The actual depth of each pier varied depending upon the
actual depth of the bearing stratum. Each bidder established a unit cost per linear foot
for extra depth of piers in their original bid. Based upon the additional depth of piers,
including steel casings (required if water is encountered), including reinforcing steel,
dowels and concrete, the cost of this item is $10,877.89. This item will be paid out of the
Building Contingency budget. Staff approved this item.
Change Order No.5
Change Order No. 5 specifically includes four items.
■ Item A is for the furnishing of materials and labor to install four new exhaust fans in the
new addition. The fans were originally planned to be removed from the existing building
and relocated to the new addition. However, after considering the importance of
maintaining the operation of the current facility, it was determined that it was in the best
interest of the project and the patrons to install four new exhaust fans in lieu of removing
the old ones at this time. The cost of this item is $1,856.97. This cost of this item is
allocated out of the Building Contingency budget.
■ Item B is for the furnishing of materials and labor to install noncombustible plywood
decking on top of the structural metal deck at the curved roof assembly over the building
lobby. It was the opinion of the Contractor and agreed upon by the Architect that the
addition of this plywood decking would allow a more uniform or consistent curve to be
maintained. This will allow the metal roof panels to maintain a more aesthetically
pleasing curvature with a sound, uniform substrate. The cost of this item is $8,733.46.
This cost of this item is allocated out of the Building Contingency budget.
■ Item C is for the furnishing of materials and labor to install a below ground conduit bank
for telephones and computer links between the Convention Center, Community Activities
Center and Library. The cost of this item is $ 7,381.51. This cost of this item is allocated
out of the Owner Direct Expenses budget.
March 1, 2001 (12:12PM)
■ Item D is for the furnishing of materials and labor to connect the lighting system for the
entire library facility to the Energy Management System utilized by the Facility Services
Division of Public Works. This system will allow for override flexibility, which may be
required by the Library staff on occasion. The connection to the energy management
system will allow for energy cost savings once the project is operational. The cost for this
item is $ 5,504.66. This cost of this item is allocated out of the Building Contingency
budget.
Change Order No. 5 totals $ 23,476.60.
Staff recommends approval.
R. M9 0 Iva
March 1, 2001 (12:12PM)
NATIONAL CONSTRUCTION LAW CENTER, INC.
CHANGE ORDER
This is CHANGE ORDER NO.4 (Four l to Contract dated MAY 30, 2000 for the construction of
THE CITY OF GRAPEVINE PUBLIC LIBRARY EXPANSION
Between T.W. FOSTER, INC. (Contractor) and CITY OF GRAPEVINE TEXAS (Owner).
Pursuant to Paragraph 15 of the above referenced Contract, the Contractor is hereby directed to make
the following changes in the Work:
A. Adjust payment schedule to reflect and accommodate actual costs for pier drilling
to include additional, casings, drilling rig and concrete, complete in place: $10,877.89
TOTAL CHANGE ORDER AMOUNT: $10,877.89
The Contract Price as adjusted through Change Order No. 3 was:
The Contract Price is hereby increased in the amount of:
$4,925,478.44
$10,877.89
The Contract Price taking into account the effect of this Change Order, shall be and is: $4,936,356.33
The Date of Substantial Completion, as specified in the Contract shall not change and shall remain May
25, 2001. Final Project Completion shall remain June 23, 2001.
Execution of this Change Order by the Contractor shall have the effect set forth in Subparagraph 15(d) of
the above -referenced Contract.
OWNER ARCHITECT CONTRACTOR
City of Grapevine Phillips Swager Associates, Inc. T. W. Foster, Inc.
By: By: BY:
(SIGNATURE) (SIGNATURE) (SIGNATURE)
(TfrLE) (TITLE) (TITLE)
(DATE)
Approved by Staff: February 19 2000
(DATE)
NCLC DOCUMENT 20 * CHANGE ORDER * 81994
NATIONAL CONSTRUCTION LAW CENTER, INC., PO BOX 57308, ATLANTA, GEORGIA 30343
Page 1 or 1
(DATE)
February 7, 2001
Elbridge Christison
City of Grapevine
Grapevine, Texas 76051
RE: Grapevine Public Library
Dear Mr. Christison,
1606 lNousi L,%- CouRT * ARuN=N. TExAs 76011 * METRO 817-265-9162
Below is the price breakdown for the pier depth report (revised) on Grapevine Public Library
Adjusted Casing
45,280.00
Added drilling
$3,365.04
Added Concrete
$10,255.36
16.5 yds extra concrete
$1,237.56
Bonding
$275.00
Liabitity Insurance
$15.21
Umbrella Insurance
$15.94
Builder Risk Insurance
$4.94
Subtotal
$9,688.99
10% OHV:l
988.90
Total
$10,877.89
If you have any questions or need more information please call me.
Thank You,
Jim Butler
Project Manager
T.W. Foster, Inc.
11
AN EGUAL OPPORTUNITY EMPLOYER
NATIONAL CONSTRUCTION LAW CENTER, INC.
CHANGE ORDER
This is CHANGE ORDER NO. 5 (Fivel to Contract dated MAY 30. 2000 for the construction of
THE CITY OF GRAPEVINE PUBLIC LIBRARY EXPANSION
Between T.W. FOSTER. INC. (Contractor) and CITY OF GRAPEVINE TEXAS (Owner).
Pursuant to Paragraph 15 of the above referenced Contract, the Contractor is hereby directed to make
the following changes in the Work:
A. Furnish materials and labor to install four new exhaust fans in lieu of utilizing
existing fans, complete in place: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ $1,856.97
-----------------------------
B. Furnish materials and labor to install fire rated plywood decking on roof canopy to
provide uniform substrate, complete in place_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ $8,733.46
C. Furnish materials and labor to install conduit bank and vaults for telephone and
data run cabling, complete in-place: ------ $7,381.51
D. Furnish materials and labor to connect library lighting system to Facility Services
Emergency Management System, complete in place: $5,504.66
TOTAL CHANGE ORDER AMOUNT: $23,476.60
The Contract Price as adjusted through Change Order No. 4 was: $4,936,356.33
The Contract Price is hereby increased in the amount of: $23,476.60
The Contract Price, taking into account the effect of this Change Order, shall be and is: $4,959,832.93
The Date of Substantial Completion, as specified in the Contract shall not change and shall remain May
25, 2001. Final Project Completion shall remain June 23, 2001.
Execution of this Change Order by the Contractor shall have the effect set forth in Subparagraph 15(d) of
the above -referenced Contract.
OWNER ARCHITECT CONTRACTOR
City of Grapevine Phillips Swager Associates, Inc. T. W. Foster, Inc.
By: By: By:
(SIGNATURE) (SIGNATURE) (.SIGNATURE)
(TITLE) (TITLE) (TITLE)
(DATE) (DATE) (DATE)
Approved by City Co un cif:
NCLC DOCUMENT 20 * CHANGE ORDER * 8 1994
NATIONAL CONSTRUCTION LAW CENTER, INC., PO BOX 57308, ATLANTA, GEORGIA 30343
Page 1 of 1
Feb -20-01 10z02A T.W. Fopr.,Limr-, Inc--- 817-274-2972 P - O:L
T%Afi= -rexA5 7e301 -1 el 7-2GS-0-1 S2
T. W. FOSlr r = R 1 1 Gas Nc)u_L64_ CoLj=T
caN-rm^a-rC)940
February 20, 2001
Elbridge Christiszon
City of Grapevine
Grapovine, Texas 76051
RE: Grapevine Public Ubrary
Dear Mr. Christison,
Below is the prfce for 4 new exhaust fans in lieu orexistingtanz (Raviseo)
Ernaust Fans
$1,632.00
Bonding
$50.00
Uablitry insurance
$2.59
Umbrella Insurance
52_72
Builder Risk Insurance
40.84
Subtotal
$1,688.15
10% OH'LP
$168,E2
Total
$1,858.97
If you have any questions or need more infonnation please "17 me,
,t Thank Yo
,aject Manager
W Foster, Inc.
S
AN EQUAL OPPORTUNITY EMPLOYER
Received Feb -20-2001 09:51 am From -817 274 2972 To -CITY OF GRAPEVINE Page 001
Fab -16-01 02 c SIP TW FOSTER INC 817 2zb-t^�jr-1e_d+ r _ vi
lr%A/F
T. W. FO S T E )R I N C • -1 BOG INcu=rcuei- COUP: r + A :4uNL N. TexAs 76001 I MEma el 7 -20n -Bl 62
caNTRACTORS
February 18, 2001
Bob Price
City or Grapevine
Grapevine, Texas 76051
RF_ Grapewne Public Library
Dear Mr. Price,
BeloW is me breakdown for the frre rated plywood decking
General Requirement
$3,208.00
Labor Burden
$1,184.50
Material
;3,300.00
Bonding
$225.00
UabilRy Insurance
$5.24
Umbrella insurance
512.80
BuikW Risk Insurance
$3.97
Subtotal
$7,939.51
f0% OHIP
$793.0
Total
,18,738.46
K you have any questions or need more information please call me.
Thank Yo
(P7 Butler
Ject Manager
.W. Foster, Inc.
S
AN EQUAL OPPORTUNITY EMPLOYER
Received Fab -16-2001 02:51Pm From -617 275+3224 To -CITY OF GRAPEVINE Pace 001
February 14, 2001
Bob Price
City of Grapevine
Grapevine, Texas 76051
RE: Grapevine Public Library
Dear Mr. Price,
1606 (Nous, TIAL COURT 0 ARuNcs i N, TExoa-,s 76011 • METRo B17-265-91 62
Below is the price difference between the conduit bank for the telephone and data runs
Addition cost conduit
$9,331-00
Deduct for concrete
-$2,845.00
Bonding
$200.00
Liability Insurance
$10.30
Umbrella Insurance
410-81
Builder Risk Insurance
$3.35
Subtotal
$6,1710.46
10% OHIP
1M.0
Total
$7,381.51
Ifyou have any questions or need more information please call me.
Thank You,
Jim Butler
Project Manager
T.W. Foster, Inc.
S
AN EQUAL OPPORTUNITY EMPLOYER
M
FOSTER
CONTRACTORS
February 14, 2001
Elbridge Christison
City of Grapevine
Grapevine, Texas 76051
RE. Grapevine Public Library
Dear Mr. Christison,
1606 (NDusrRLAL Couar • ARuNoroN, TEx s 76011 • ME -Ro 617-265-9162
Below is the price for CSI to wire library to EMS
CSI
$4,836.00
Bonding
$150.00
Liability Insurance
$7.68
Umbrella Insurance
$8.06
Builder Risk Insurance
$2.50
Subtotal
$5,0044
100A OHIP
500 42
Total
$5,504.66
If you have any questions or need more information please call me.
4�
Thank You,
Jim Butler
Project Manager
T.W. Foster, Inc.
S
AN EQUAL OPPORTUNITY EMPLOYER