HomeMy WebLinkAboutItem 05 - Dove Loop RoadMEMO TO
FROM:
MEETING DATE:
SUBJECT
RECOMMENDATION:
STEM # _,�--
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
ROGER NELSON, CITY MANAGER //V
DECEMBER 5, 2000
ENGINEERING SERVICES CONTRACT/ DOVE LOOP ROAD
City Council consider awarding an Engineering Services Contract for Dove Loop Road
between North Main Street and Dove Road, to Huitt Zollars, Inc. in an amount not to
exceed $ 840,000, authorize staff to execute said contract, and take any necessary
action.
FUNDING SOURCE:
Funds are currently available and programmed as follows:
Funding Source
Account
Amount Award
Percent
Peripheral Street Fees
178-21524-000
$ 31,476
.3%
99 GO Bonds
178-78103-010
$ 1,100,156 $840,000
9.4%
00 GO Bonds
178-78101-011
$ 66,964
.6%
02 GO Bonds
$ 5,595,325
48.3%
03 GO Bonds
$ 4.795.325
41.4%
TOTAL $11,589,246 $840,000
Budget
Amount Award
Percent
Engineering
$ 1,091,100 $840,000
9.4%
Right -of -Way
$ 66,850
.6%
Construction
$ 8,379,216
72.3%
Contingency
$ 2.052.080
17.7%
TOTAL $11,589,246 $840,000
BACKGROUND:
The Dove Loop Road project will include construction of Dove Loop Road extension
from the Dove Road / Dove Loop Road intersection on the west to North Main Street on
on the east, and then a section south to Northwest Highway. This project, given the
nature and extent of the new construction, will be an extremely challenging endeavor.
November 29, 2000 (10:54AM)
The proposed roadway crosses Corps of Engineer property at two separate locations.
The Corps of Engineers has recently initiated a program to identify and protect
Environmentally Sensitive Areas (ESA's) around Lake Grapevine. The Corps Staff and
the City Staff have been working closely to identify roadway and utility corridors to be
reserved for future needs through and adjacent to these ESA's. The staff of Huitt Zollars
has supported the City with both engineering and environmental scientist services in the
coordination efforts with the Corps. In light of the increased interest in environmentally
sensitive areas around the lake, Staff feels that it is important to proceed with the design
of this project with Huitt Zollars as it is the firm most familiar with this project and the
environmental issues.
Staff proposes to use Huitt Zollars, Inc. for this work based upon our past experiences
with this firm. Huitt Zollars designed both the Mustang Drive project from William D.
Tate Avenue to SH 26 and the Pool Road project from SH 26 to Hall -Johnson Road for
the City. Both projects were very successful. We believe that Huitt Zollars is the best
choice for this project and will provide us the best opportunity to complete this project
with few problems and with positive results. Based upon our knowledge of the firm and
our experience with their work, staff recommends that Huitt Zollars be engaged to
perform the engineering design services for this sensitive project.
Staff recommends approval.
JSL/dsm
0:\agenda\12-05-00\ EngSrvContract_DoveLoopRd.agm
November 30, 2000 (1:22PM)
GENERAL GOVERNMENT CAPITAL PROJECTS
North Main Street
Reconstruction and widening of North Main Street from Northwest Highway north to Dove Loop Road. The roadway
will be two-lane concrete with curb and gutter. The proposed improvements include the extension of North Main
Street from its proposed terminus in the Northwest Highway project adjacent to Elliott's Hardware north to Dove
Loop Road. This project will be built with the Dove Loop Road project.
PROJECT SCHEDULE B99ill End
Design Nov -00 Jan -02
ROW Acquisition Nov -01 Jan -02
Construction Apr -02 Apr -04
FISCAL. IMPACT
Operating budget impact includes the cost of periodic street sweeping, electricity for street lights, maintenance of road
markings, and maintaining parkways on both sides of the roadway. Sealing of joints in pavement won't be needed
until FY -06.
Projected Annual
FY -2001 P`Y-2002 FY -2003 FY -2004
FY -2005
Total
,Project
LTD
Budget
Planned
Project
Expenses
09130100
FY -2001
FY -2002 FY -2003 ' FY -2004 FY -2005
Cost
Design
6,000
140,100
35,000
181,100
ROW
450
900 i
66,964
66,964
Construction
0
470,524 588,156
1,058,680
Contingency
$3,404
296,068
296,068
TOTAL:
$6,000
$140,100
$572,488 $588,156 $296,068 $0
$1,602,812
Funding
Source
114,624
66,476
181,100
1999 GO Bonds
2000 GO Bonds
66,964
66,964
2002 GO Bonds
439,048
222,588
661,636
2003 GO Bonds
365,568
296,068
661,636
Periphery Fees
6,000
25,476
31,476
TOTAL:
$6,000
$140,100
1 $572,488
$588,156
1 $296,068
$0
51,602,812
Operating budget impact includes the cost of periodic street sweeping, electricity for street lights, maintenance of road
markings, and maintaining parkways on both sides of the roadway. Sealing of joints in pavement won't be needed
until FY -06.
Projected Annual
FY -2001 P`Y-2002 FY -2003 FY -2004
FY -2005
; O eratin Impact
Bud et Planned Planned Planned
Planned
Total
Personnel Ex enses
0
Supplies
0
Maintenance
685
1,369
2,054
Services
450
900 i
1,350
Capital Outlay
0
Total
$0 ' , $0 50 $1,135
52,269
$3,404
GENERAL GOVERNMENT CAPITAL PROJECTS
Dove Loop Road
Dove Loop Road is a new roadway connecting Dove Road to North Main Street. It is to be a four -lane undivided
roadway with expanded intersections. A portion of the roadway east of the wastewater plant will be four -lane
divided as the alignment of the proposed roadway tracks the alignment of the existing TU Electric transmission
towers. The transmission towers will be located in the proposed median. A hike and bike trail will be constructed
as part of this project.
PROJECT SCHF�E Bgziu End
Design Nov -00 Jan -02
Construction Apr -02 Apr -04
FISCAL IMPACT
Project
Fz enses
LTD
09130/00
Budget
FY -2001
Planned
; FY -2002 FY -2003 FY -2004 FY -2005 `
Total
Project
Cost
Budget Planned Planned Planned
Planned
Tgtal
Personnel Expenses
0"
Su plies
Design
Construction
Contingency
TOTAL:
$0
796,250
$796,250
113,750
2,934,540
$3,048,290
3,679,300
$3,679,300
1,662,594
$1,662,594
$0
910,000
6,613,840
1,662,594
$9,186,434
1,250
2,500
3,750
Ca ital Outlay0
.
Total , ,
:Funding
$6,440
39,660
Source
$0
796,250
$796,250 1
122,806
2,925,484
$3,048,290
1,208,205
2,471,095
$3,679,300
1,662,594
$1,662,594
$0
919,056
4,133,689
4,133,689
$9,186,434
1999 GO Bonds
2002 GO Bonds
2003 GO Bonds
TOTAL:
IMPACT ON OPERATING BU GFT
Operating budget impact includes the cost of periodic street sweeping, electricity for street lights, maintenance of
road markings, and maintaining parkways on both sides of the roadway. Sealing of joints in pavement won't be
needed until FY -06.
Projected Annual
FY -2001 FYCj02 2003 ' FY -2004
FY 2005
O ` rahn ' Dn act
Budget Planned Planned Planned
Planned
Tgtal
Personnel Expenses
0"
Su plies
0
Maintenance
1,970
3,940
5,910
Services
1,250
2,500
3,750
Ca ital Outlay0
.
Total , ,
$0 ., ,;, $0 50 "$3,220
$6,440
39,660
Dove Road Medians
Installation of an attractive median where the center tum lane now exists on Dove Road from Kimball to Dove Loop.
This project includes the removal of the existing tum lane and construction of a planted, irrigated, median with turn
lanes at all the existing street intersections.
PROTECT SCHEDULE B1in Did
Design
Nov -00 Jan -02
Construction Apr -02 Apr -04
Operating budget impact includes the cost of electricity for street lights and maintaining the medians.
Total
Project
LTD
09130/00
Budget
FY -2001
Planned
FY -2002 FY -2003 F Y 2004 FY -2005
Project
Cost
Expenses
Design included
in Dove East
Extension
Construction
398,348 308,348
706,696
Contingency
$0
93,304
$398,348 $401,652 $0 $0
93,304
$800,000
TOTAL:
$0
Funding'
Source
398,348
401,652
800,000
2002 GO Bonds
TOTAL:
$0
$0
$398,348
$401,652
$0
$0
$800,000
Operating budget impact includes the cost of electricity for street lights and maintaining the medians.