HomeMy WebLinkAboutItem 11 - Hilton Force Main ProjectE,
MEMO TO:
FROM:
MEETING DATE:
SUBJECT:
RECOMMENDATION:
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
ROGER NELSON, CITY MANAGER*/
DECEMBER 19, 2000
ENGINEERING SERVICE CHANGE ORDERS NUMBER TWO
AND THREE FOR THE HILTON FORCE MAIN PROJECT
City Council to consider Change Orders number 2 and 3 to the Hilton Force Main design
contract of Montgomery Watson Americas, Inc. in the amount of $7,906.00 and
$27,089.00 respectively and authorize the City Manager as signatory.
FUNDING SOURCE:
Funds are available as follows:
i Funding Source
Account
Amount
Award
Percent
96 Utility Bonds
200-48940-534-2-000004SW
$ 484,328
17.3%
99 Utility Bonds
200-48940-534-5-000002SW
$ 25,375
.9%
99 Utility Bonds
200-48940-534-5-000003SW
$ 35,100
1.3%
99 Utility Bonds
200-48940-534-5-000004SW
$2,059,555
$27,089
73.8%
WW Impact Fees
200-48930-534-6-000001
$ 161,419
5.8%
Fellowship Church
178-21560
$ 24.600
$7,906
.9%
TOTAL
$2,790,377
$34,995
100%
Budget
Amount
Award
Percent
Engineering
$ 198,750
$34,995
7.1%
Construction
$2,253,000
80.7%
Testing/Surveying
$ 60,587
2.2%
ROW Acquisition
$ 58,000
2.1%
Contingency
$ 220.040
7.9%
TOTAL
BACKGROUND:
$2,790,377 $34,995 100%
Currently, sewage is conveyed from the northeast portion of Grapevine by the Hilton Lift
Station and force main, which was constructed when the DFW Hilton Hotel developed
16 years ago. The Grapevine Utility Master Plan called for upgraded facilities when
December 13, 2000 (1:59PM)
additional development exceeded the capacity of the lift station. The development of
multifamily and commercial development in the area necessitates the initiation of this
project.
Although the lift station was upgraded recently, the force main needs to be enlarged.
Montgomery Watson Americas Inc. was selected to provide the engineering design
services for the force main.
Change Order Number 2
During the design phase the Fellowship Church platted the property that the lift station is
located on and requested that the pipeline be relocated to allow the Church to better
utilize their property. This request necessitated a redesign with an additional engineering
fee was $7,906. The Fellowship Church reimbursed the City of Grapevine this amount.
Change Order Number 3
The current force main route is Bass Pro Dr. to State Highway 26 to Ruth Wall and
terminates at Boyd and Wildwood. This alignment was utilized for the design of new
facility. The existing force main must be kept in service during construction, which
means the new force main must be built in a new easement. Since Staff was
unsuccessful in negotiating a new easement on Ruth Wall Street a new alignment and
redesign of that section of the force main was done. The new alignment will follow
State Highway 26 to Boyd and north on Boyd to Wildwood. The redesign fee is
$27,089.
Staff recommends approval of change order number 2 and 3 in the amount of $7,906
and $27,089 respectively.
MS/ms