HomeMy WebLinkAboutItem 15 - Grapevine Public LibraryMEMO TO:
FROM:
MEETING DATE:
SUBJECT:
RECOMMENDATION:
ITEM • f 5
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
ROGER NELSON, CITY MANAGER fW
DECEMBER 19, 2000
GRAPEVINE PUBLIC LIBRARY — CHANGE ORDER NO. 3
City Council consider approving Change Order No. 3 to the Grapevine Public Library
Expansion Project with T. W. Foster, Inc., Contractors in the amount of $ 139,113.66,
authorize staff to execute said Change Order, and take any necessary action.
BUDGET
Amount
Award
Percent
Library Building Account
Planning/Design
$ 613,805.59
100-48840-313-1
8.8%
Construction
4,832,487.00
177-48840-010-31
69.6%
Owner Direct Expenses
675,000.00
71,555.40
9.7%
Furnishings and Signage
650,000.00
55,185.98
9.4%
Contingency
171.326.65
12.372.28
2.5%
TOTAL
$ 6,942,619.24
139,113.66
100.0%
FUNDING SOURCE:
December 13, 2000 (3:55PM)
Amount
Award Percent
Acct. Nos.
Library Building Account
$ 14,750.35
0.21%
100-48840-313-1
99 GO Bonds
1,000,152.00
14.40%
177-48840-010-31
00 GO Bonds
2,879,893.89
41.50%
177-48840-011-31
00-A GO Bonds
2,875,000.00
139,113.66 41.40%
177-48840-012-31
99 GO Bond Int.
67,000.00
0.96%
177-48840-010-31
00-A GO Bond Int.
103,675.00
1.50%
177-48840-011-31
Contractor Reimbursement
2.148.00
0.03%
177-48840-010-31
TOTAL
$ 6,942,619.24
139,113.66 100.00%
December 13, 2000 (3:55PM)
a BACKGROUND:
The Contract for the construction of the Grapevine Public Library improvements was
awarded to T.W. Foster, Inc. Contractors, Inc. by the City Council on April 18, 2000.
The Notice to Proceed for the project was issued on May 30, 2000. The original time
allotted for the contract is 390 days.
According to the contract, the Contractor is scheduled to be substantially complete on
May 25, 2001. We anticipate that the construction of Phase I (the new addition) will be
completed in late February or early March.
Change Qrder Number 3
Change Order No. 3 specifically includes seven items.
■ Item A is for the furnishing of materials and labor to install end of panel resource
signage. These are signs, which will assist the patrons in locating which library
resources are located on specific shelves. The cost for this item is $7,482.38. This
item is under budget and will be paid out of the Furnishings and Signage budget.
■ Item B is for the furnishing of materials and labor to install Category 5
Communications data cabling for Telecommunications, Book Security (Checkpoint),
Computer Network, Internet, Courtesy Phones, Faxes/Modems, a conduit bank
between the Library, Community Activities Center and Convention Center. The cost
for this item is $71,555.40. This item is below the budgeted amount allocated in the
Owner Direct Expenses budget.
■ Item C is for the furnishing of materials and labor to construct a solid wall from the
finished floor up to 42 inches in lieu of a full height glass wall in the General
Collection Room, No. 146 adjacent to the Computer Training Room, No. 139. The
cost for this item is $ 414.07.
■ Item D is for the furnishing of materials and labor to install a ceiling mounted
television and VCR bracket . This item will be located in the staff lounge, Room No
129. The cost for this item is $ 635.98.
■ Item E is for the furnishing of materials and labor to construct and install a Local
History Display Case including glass doors and 18" Marlite shelves. The cost for this
item is $1,107.90.
• Item F is for the furnishing of materials and labor to remove two existing roof top
units and replace with two 5 -ton roof heating and cooling units (RTU) including built
up curbs. These existing units are approximately 14 years old. The cost of replacing
,.. these two units is $ 10,214.33.
December 13, 2000 (3:55PM)
Item G is for the furnishing of materials and labor to construct and install the Main
Circulation Desk, Reference Desk and two OPAC tables. The cost for this item is
$47,703.60. This item is below the budgeted amount allocated in the Furnishings
and Signage budget.
Change Order No. 3 totals $ 139,113-66.
Staff recommends approval.
December 13, 2000 (3:55PM)
IN
NATIONAL CONSTRUCTION LAW CENTER INC.
CHANGE ORDER
This is CHANGE ORDER NO 3 (Three) to Contract dated MAY 30, 2000 for the construction of
THE CITY OF GRAPEVINE PUBLIC LIBRARY EXPANSION
Between T.W. FOSTER. INC. (Contractor) and CITY OF GRAPEVINE, TEXAS (Owner).
Pursuant to Paragraph 15 of the above referenced Contract, the Contractor is hereby directed to make
the following changes in the Work:
A.
Furnish materials and labor to install end of panel resource signage, complete in
.Place---------------------------------------------------------------
$7,482.38_
B.
Furnish materials and labor to install Communication, Data, Phone, CCTV,
Computer Wiring throughout_completq in place_ ------------------------------
$71,555.40
71,555---
C.
Furnish materials and labor to install a solid wall up to 42" from the finished floor
and glass from the top of the solid wall to the ceiling in lieu of a full height glass
wall in the General Collection, Room No. 146 adjacent to the Computer Training
co
Room, No. 139, mplete in place -------------------------------------------$414.07
Room- ------ --- -t --
_
D.
Furnish materials and labor to install a ceiling mounted Television and VCR shelf
bracket, complete in place------------------------------------------------------
8_
E.
Furnish materials and labor to install Local History Display Case including glass
doors and 18" Marlite shelves,_ complete in place_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ------------1,107.--
$1,107.90
F.
Furnish materials and labor to remove and replace two (2) 5 -ton Roof Top
Heating and Cooling Units_�RTU) including built-up curbs, complete in place: _
$10,214.33
G.
Furnish materials and labor to install Marlite and 1-1/4" granite Circulation,
Reference and (2) OPAC tables, complete in place
$47,703 60
TOTAL CHANGE ORDER AMOUNT: $139,113.66
The Contract Price as adjusted through Change Order No. 2 was:
The Contract Price is hereby increased in the amount of:
$4,786,364.78
$139,113.66
The Contract Price, taking into account the effect of this Change Order, shall be and is: $4,925,478.44
The Date of Substantial Completion, as specified in the Contract shall not change and shall remain May
25, 2001. Final Project Completion shall remain June 23, 2001.
Execution of this Change Order by the Contractor shall have the effect set forth in Subparagraph 15(d) of
the above -referenced Contract.
NCLC DOCUMENT 20' CHANGE ORDER' 81994
NATIONAL CONSTRUCTION LAW CENTER, INC., PO BOX 57308, ATLANTA, GEORGIA 30343
Page 1 of 2
i i i
CHANGE ORDER
OWNER ARCHITECT CONTRACTOR
City of Grapevine Phillips Swager Associates, Inc. T. W. Foster, Inc.
By.gy; By:
(SIGNATURE) (SIGNATURE) (SIGNATURE)
(TITLE) (TITLE) (TITLE)
(DATE) (DATE)
Approved by City Council: December 19. 2000
NCLC DOCUMENT 20' CHANGE ORDER ' 81994
NATIONAL CONSTRUCTION LAW CENTER, INC., PO BOX 57308, ATLANTA, GEORGIA 30343
Page 2 of 2
(DATE)