HomeMy WebLinkAboutItem 18 - Ruth Wall RoadMEMO TO: HONORABLE MAYOR AND MEMBERS O THE CITY COUNCIL FROM: ROGER NELSON, CITY MANAGER MEETING DATE: SUBJECT RECOMMENDATION: JANUARY 15, 2002 CHANGE ORDER MECHANICALLY FOUNDATION # 2 - RUTH WALL ROAD (TIF II) STAABILIZED EARTH (MSE) WALL City Council consider approving Change Order # 2 to the Ruth Wall Road (TIF II) Construction Project in an amount of $ 47,347.02 to remove unsuitable material and replace it with special backfill material for the low water crossing north of Wildwood Lane, authorize staff to execute said change order, and take any necessary action. FUNDING SOURCE: Funds are currently available in Account # 173-48899-0003, TIFII / Ruth Wall Construction. BACKGROUND: TIF improvements for Opryland Texas include improvements to Ruth Wall Road to serve as the alternate entrance into the Opryland Hotel and provide improved traffic flow for the existing residents of Grapevine. The Ruth Wall Road project scope includes the replacement of the existing low water crossing with Mechanically Stabilized Earth (MSE) Walls located above the 100 -year flood elevation for Lake Grapevine. Excavation of the low water crossing has revealed that the subsurface soils beneath portions of the MSE Wall are unsuitable due to their inability to support the weight of the tallest wall sections near the low water crossing, approximately 30 feet in height. A geo- technical study was conducted to determine what remedial measures would be required to provide a stable foundation sub -grade. The geo-technical engineer recommended that the existing materials be removed and replaced with crushed rock and cement treated materials depending on the type and depth of soil encountered during removal of the existing materials. 0:\agenda\1-15-02\CO#2 — Ruth Wall TIF II January 10, 2002 (8:53AM) This over excavation of the existing material below the wall foundation and replacement with the recommended material was not included in the original project scope of work. The estimated quantity to be removed and replaced is approximately 2,027 cubic yards. This will be replaced with the crushed rock or cement treated materials. Change Order # 1 was a reduction in the contract price of $ 3,050.00. Staff recommends approval. 0:\agenda\1-15-02\CO#2 — Ruth Wall TIF II January 10, 2002 (8:53AM) CONTRACT MODIFICATION AGREEMENT C.O. # 2 A change to the terms of the Contract below is agreed as follows: PROJECT: TIF IMPROVEMENTS FOR OPRYLAND TEXAS, PHASE 2 - RUTH WALL ROAD, LIFT STATION AND SEWER IMPROVEMENTS OWNER: City of Grapevine ENGINEER: CARTER & BURGESS, INC. CONTRACTOR: AUI CONTRACTORS, INC. CHANGE ORDER NO: 2 DATE: 01-08-2002 The compensation agreed upon in this Change Order is for all costs the CONTRACTOR has incurred or may incur as a result of or relating to the changes in the scope of work whether said cost are known, unknown, foreseen or unforeseen at this time, including without limitation, any cost for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a result of this Change Order. The compensation will be for fully complete and in-place construction and the actual quantities of items installed or constructed will be measured and the quantities herein adjusted accordingly. A. CHANGE IN SCOPE OF WORK: Additional Unclassified Excavation underneath MSE Walls Provide and Install Crushed Rock - Labor, Equipment, and Material, Install Cement Treated Material - Labor and Equipment Only B. DETAILED UNIT COSTS, QUANTITIES & TOTAL CONTRACT PRICE CHANGES Change Unit Extension ITEM DESCRIPTION in Qty UNITS CY50 Price F Net Change $12,55&50 4 Unclassified Excavation 2283 W �/. vv 115 Crushed Concrete, Labor, Materials and Equipment 902 CY $26.16 $23,596.32 Complete and In Place 116 Placement of Cement Treated Material 1382 CY $8.10 $11,194.20 - Labor and Equipment Only 98220906. RWChangeOrder2.xfs CONTRACT MODIFICATION AGREEMENT C.O. # 2 B. DETAILED UNIT COSTS, QUANTITIES & TOTAL CONTRACT PRICE CHANGES (Continued) Change Unit Extension ITEM DESCRIPTION in Qty UNITS Price Net Change TOTAL THIS CHANGE ORDER C. SUMMARY OF NET CHANGES TO CONTRACT AMOUNT AND TIME $47,347.02 7riginal Contract Amount $5,889,576.70 ;hange Order No. 1 ($3,050.0% ;hange Order No. 2 $47,347.02 ;hange Order No. 3 ;hange Order No. 4 tevised Contract Amount Number of Days added to the Contract Time by this change order: 0 Days Last day of the Contract Time: No Change D. APPROVALS City of Grapevine By: Jerry L. Hodge Director of Public Works Contractor By: B rt Weathersbee Carter & Burgess Engineer By: 98220906. RW ChangeOrder2.xls Date /r �11 - C:,� Date