HomeMy WebLinkAboutItem 06 - LibraryITEM / MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: ROGER NELSON, CITY MANAGER MEETING DATE: AUGUST 6, 2001 SUBJECT: GRAPEVINE PUBLIC LIBRARY — CHANGE ORDER NO. 7 RECOMMENDATION: City Council consider approving Change Order No. 7 to the Grapevine Public Library Expansion Project with T. W. Foster, Inc., Contractors in the amount of $ 29,623.05, authorize staff to execute said Change Order, and take any necessary action. BUDGET Amount Award Percent Planning/Design $ 613,805.59 8.8% Construction 4,857,600.36 70.0% Owner Direct Expenses 675,000.00 9.7% Furnishings and Signage 650,000.00 9.4% Contingency 146.213.29 29.623.05 2.1% TOTAL $ 6,942,619.24 29,623.05 100.0% FUNDING SOURCE: Amount Award Percent Acct. Nos. Library Building Account $ 14,750.35 0.21% 100-48840-313-1 99 GO Bonds 1,000,152.00 14.40% 177-48840-010-313 00 GO Bonds 2,879,893.89 41.50% 177-48840-011-313 00-A GO Bonds 2,875,000.00 29,623.05 41.40% 177-48840-012-313 99 GO Bond Int. 67,000.00 0.96% 177-48840-010-313 00-A GO Bond Int. 103,675.00 1.50% 177-48840-011-313 Contractor Reimbursement 2,148.00 0.03% 177-48840-010-313 TOTAL BACKGROUND: $ 6,942,619.24 29,623.05 100.00% The Contract for the construction of the Grapevine Public Library improvements was awarded to general contractor, T.W. Foster, Inc. by the City Council on April 18, 2000. The July 31, 2001 (12:49PM) Notice to Proceed for the project was issued on May 30, 2000. The original time allotted for v' the contract was 390 days. The construction of Phase One (the new addition) was completed June 12, 2001 and the Library opened for public service on Wednesday, June 13, 2001. Phase Two (renovation of the old library and interconnection with all of Phase One) is scheduled to be completed by October, 2001. Change Order No. 7 specifically includes 11 items (A through K). All items will be paid from the Construction Contingency allocation. Item A is a credit of $4,875.00 to the City from TW Foster for the purchase of asphalt used in the construction of the new Library Access Road. The Contractor was required to construct a temporary access road for the construction of the project. However, City crews constructed the road with materials provided by the Contractor per an agreement reached at a later date. Item B is the installation of glass doors in lieu of solid -core wood doors for the five study rooms in Phase Two. The Library Director requested this change for security purposes. The cost of this substitution is $4,308.49. Item C is the installation of additional Marlite wood end panels to the circulation and reference desks. The cost for this item is $910.81. Item D is the installation of irrigation related devices necessary for the Irrigation System. The cost for this item is $5,795.92. Item E is for additional labor and installation of equipment, conduit and junction boxes necessary for the completion and total system integration of the telephone, data and fiber optic delivery system connecting the Library, Convention Center and Community Activities Center. The cost for this item is $4,552.65. Item F is a $5,740.77 reimbursement to TW Foster, the contractor, from the City for modifications pertinent to the scope of surveying and architectural services. These costs will be recouped from the Architect for errors in the plans. City involvement is required due to lack of contract between Contractor and PSA Architects. Since PSA Architects does not have a contractor, the City is involved. Item G is the furnishing of materials and labor to install a water line to serve Roof Top Unit #10 humidifier and the installation of two roof top water hydrants. The hydrants are necessary for the periodic cleaning of the RTU coils. The cost for this item is $4,404.00. Item H is for the miscellaneous items that were necessary to get Phase One of the building operational for the opening on Wednesday, June 13, 2001. These items consist of the relocation and installation of electrical devices including, doorbell, isolated ground quad August 1, 2001 (10:51 AM) receptacle in computer room, 50A circuit to stove, fixture in electrical room and Room 114 switch. The cost for this item is $1,168.82. Item I is the furnishing of materials and labor to install marble thresholds at the transition of restrooms, sickroom and hallways, installation of "Teen Zone" plastic explosion -proof lens covers, two "Check Point" cabinets, Friends' Closet floor tile and Program Room corner guards and doors. The cost for this item is $2,698.42. Item J is the labor and materials required for the extension of the 80' glass wall between the Children's Area and the General Collection. The cost for this item is $519.98. Item K is the furnishing of materials and labor to install specified landscape changes including installation of Purple Winter Creeper and Jute netting in lieu of hydro -mulch. The cost for this item is $4,398.19. Change Order No. 7 totals $29,623.05. Staff recommends approval. August 1, 2001 (10:36AM) E NATIONAL CONSTRUCTION LAW CENTER INC. CHANGE ORDER This is CHANGE ORDER NO. 7 (Seven) to Contract dated MAY 30. 2000 for the construction of THE CITY OF GRAPEVINE PUBLIC LIBRARY EXPANSION Between T.W. FOSTER. INC. (Contractor) and CITY OF GRAPEVINE TEXAS (Owner). Pursuant to Paragraph 15 of the above referenced Contract, the Contractor is hereby directed to make the following changes in the Work: A. Monetary credit to the City of Grapevine for the purchase of asphalt at contractor's expense for the construction of Library Access Road: ----------------------------------------------------------------------------------------------------------------------- ($4,875.00) B. Install glass in lieu of solid -core wood for doors numbered 141, 142, 143, 144, 145 in study rooms on Phase II: --------------------------------------------------------------------------------------------------------------------- $4,308.49 C. Provide labor and materials for installation of Marlite wood to the end panels of the circulation and reference desks: ------------------------------- ------------------------------------------------------------------------------------------ $910.81 D. Provide labor and materials for installation of additional 2" double check valve, 2" flow meter and conducting wire for Irrigation System redundant back-up, complete in place: --------------------------------------------------------------------------------------------------------------------- $5,795.92 E. Provide labor and materials for installation of (3) 2" PVC conduits, flush mount boxes, masonry cores and U(G junction box for completion of telephone, data and _fiber optic delivery system: complete in place: $4,552.65 F. Reimbursement to TW Foster, Inc. for additional services and fee modifications to surveying and architectural services: -------------------------------------------------------------------------------------------- - $5,740.77 G. Provide labor and materials to provide 1/2" water line to serve humidifier on RTU No. 10 and install two (2) rootop water hydrants, complete in place: - - - ------------------------------- ----------------------------------------- $4,404.00 H. Provide labor and materials for relocation and installation of electrical devices including, doorbell, isolated ground quad receptacle in computer room, 50A circuit to stove, fixture in electrical room an Room 114 switch, complete in place: - ---------------------------------------------------------------- - ------ -- ------------------------ $1,168.82 I. Provide labor and materials to install marble thresholds, Teen Zone plastic explosion -proof lens covers,.two "Check Point" cabinets, Friends' Closet floor tile, Program Room corner guards and doors, complete in place: $2,698.42 J. Provide labor and materials to extend 80' glass wall between the Children's Area and the General Collection , complete in place: $519.98 K. Provide specified landscape changes including installation of Purple Winter Creeper and lute nettinq in lieu of hydro -mulch: $4,398.191 TOTAL CHANGE ORDER AMOUNT: $29,623.05 The Contract Price as adjusted through Change Order No. 6 was: $4,974,617.95 The Contract Price is hereby increased in the amount of: $29,623.05 The Contract Price, including the effect of this Change Order, shall be and is: $5,004,241.0 NCLC DOCUMENT 20 * CHANGE ORDER * 8 1994 NATIONAL CONSTRUCTION LAW CENTER, INC., PO BOX 57308, ATLANTA, GEORGIA 30343 Page 1 of 2 NATIONAL CONSTRUCTION LAW CENTER INC. CHANGE ORDER The Date of Substantial Completion, as specified in the Contract shall not change and shall remain May 25, 2001. Final Project Completion shall remain June 23, 2001. Execution of this Change Order by the Contractor shall have the effect set forth in Subparagraph 15(d) of the above -referenced Contract. OWNER City of Grapevine By. (SIGNATURE) (TITLE) (DATE) Approved by Cily Council: August 6 2001 ARCHITECT Phillips Swager Associates, Inc. B4 +� __ (SITURE D (TITLE) EN CONTRACTOR (SIGNATb17ET (TITLE) (DA TV NCLC DOCUMENT 20 * CHANGE ORDER' 81994 NATIONAL CONSTRUCTION LAW CENTER, INC., PO BOX 57308, ATLANTA, GEORGIA 30343 Page 2 of 2 Bob Turman From: David Booher [dboohera@ci.grapevine.tx.us] ent: Tuesday, July 03, 2001 2:47 PM To: Cc: David Booher Subject: Updated Memo Bob asked if I would add some background info .... here it is. I////ll1/llllllllll/11111/l1/11/11/11111111 MEMO FOR RECORD 3 JULY 2001 GRAPEVINE LIBRARY: CHANGE ORDER #7, ITEM A, ACCESS ROAD CREDIT TW Foster, (Jim Butler) voiced concern early on in the project, (July -August 2000) that the contract requirement to construct a typical construction type access road would not be in the best interest of the project, due to the longevity of the project and the amount of heavy construction vehicles utilizing the access road. The City of Grapevine staff agreed and further voiced concern the typical construction access would routinely have to be maintained to be effective due to the volume of heavy construction traffic. Moreover, the temporary construction access would transition to become the main public access for library patrons during the phase II portion of the project. Therefore, TW Foster and the City of Grapevine agreed on the following conditions regarding the construction of the Library Access Road on the southeast corner of the project. TWF was originally required by the contract to construct a » temporary construction access road approximately 700 LF x 20' wide x 8" minimum depth. In lieu of this temporary )access road, TWF and COG agreed that TWF would purchase asphalt material to cover the entire length of access road ." at 27' width by 2" depth and the COG would provide the base material and all installation labor. The installation of this asphalt road would not be scheduled until the conclusion of the portion of the construction project requiring concrete trucks and other heavy construction traffic. The COG would receive a credit from TWF in the amount of $4,875.00 for the purchase of the asphalt material. David Booher Construction Coordinator 111111!llllllllllllllllllllllllllllllllllllllllll David Booher City of Grapevine Construction Coordinator Phone: 817.410-3560 Mobil: 817.253-9326 Fax: 817.410-3051 June 29, 2001 Mr. Bob Price City of Grapevine 501 Shady Brook Drive Grapevine, Texas 76051 1 606 INDUSTRIAL COURT ® ARUNGTON, TexAs 7601 1 • MErRO 617-265-J1 6c - Re: Grapevine Public Library Proposed Change Order # 7 - Item B Dear Mr. Price, Below is the breakdown for the glass doors at 141, 142, 143, 144 & 145 in Phase 2 of the library: Doors $ 3,900.00 General Liability 6.19 Umbrella Liability 10.62 Overhead & Profit 10% 391.68 Total $ 4,308.49 Please let me know where you would like us to put the wood doors, since a credit cannot be given and they are property of the City. If you have any questions, please feel free to contact me. Thank You, Mary Sypinski CC: David Booher Tom Shaw . AN EQUAL OPPORTUNITY EMPLOYER T. W. FOSTER INC. CONTRACTORS June 12, 2001 Bob Price City of Grapevine Grapevine, Tx 76051 1606 INDUSTRIAL COURT 0 ARLINGTON, TExAs 7601 1 0 METRO 817-265-2162 RE: Grapevine Public Library Dear Mr. Price, Revised Pricing Below is the price for the Madite wood added to the end of the circulation and reference desks Marlite wood $560.00 Labor for installation $240.00 Bonds $25.00 Liabiality insurance $1.27 Builders insurance $0.41 Umbrella insurance $1.33 Profit and overhead $82.80 Total $910.81 If you have any questions or need more information please call me. Thank You, Buller oject r . ct Manager T.W. Foster, Inc. AN EQUAL OPPORTUNITY EMPLOYER June 29, 2001 Mr. Bob Price City of Grapevine 501 Shady Brook Drive Grapevine, Texas 76051 1606 INDUSTRIAL COURT • ARUNSTON, Texc.S 7801 1 • MEi'Ro B17-265-9162 Re: Grapevine Public Library Proposed Change Order # 7 - Revised Item D Dear Mr. Price, Below is the price for providing labor and materials for installation of additional 2" double check valve, 2" flow meter and conduction wire for Irrigation System redundant back-up and the irrigation change to 12" pop-up: 2" Double Check (letter dated 5-16) $ 474.00 2" Flow Meter (letter dated 5-16) 1,800.00 Extra Wire (letter dated 5-16) 1,000.00 Landscaper Mark-up (letter dated 5-16) 327.40 Irrigation Change to 12" Popup (letter dated 6-20) 1,645.00 General Liability 8.33 Umbrella Liability 14.29 Overhead & Profit 10% 526.90 Total S 5.795.92 If you have any questions, please feel free to contact me. Thank You, Mary Sypinski CC: David Booher Tom Shaw AN EQUAL OPPORTUNITY EMPLOYER IrWF NO T. W. FOSTER INC. r�"W b"'11111 -t �'idqlffAw June 29, 2001 Mr. Bob Price City of Grapevine 501 Shady Brook Drive Grapevine, Texas 76051 1606 INDUSTRIAL COURT 0 ARLINGTON, Texas 7601 1 0 METRO 817-265-6162 Re: Grapevine Public Library Proposed Change Order # 7 - Revised Item E Dear Mr. Price, Below is the price for providing labor and materials for installation of (3) 2" PVC conduits, flush mount boxes, masonry cores and U/G junction box for completion of telephone, data and fiber optic delivery system: Electrical $ 4,121.00 General Liability 6.54 Umbrella Liability 11.23 Overhead & Profit 10% 413.88 Total 4,552.65 If you have any questions, please feel free to contact me. Thank You, d - Mary Sypinski CC: David Booher Tom Shaw AN EQUAL OPPORTUNITY EMPLOYER April 16, 2001 1 Bob Price City of Grapevine Grapevine, TX 76051 1606 JNousTRL,%,L COURT 0 ARUNQiI N, TExAs 7601 1 e METRO B17 -265-B'1 B2 RE Grapevine Public Library Dear Mr- Price, Below is a change order recap requested by TWF (revised) PSA additional services for structural Cost occurred by TWF surveying not complete Total If you have any questions or need more information please call me. Thank You, .lim Butler Project Manager T.W. Foster, Inc. f ($2,172.35) 913.12 $5,740.77 j.1 -Q2-01 03:23P -F_W- Fos -tier-, Xnc--- 817-274-2972 P.02 T. W. FO ST M R I N C • -1606 1rjoL=-rriv,4_ COURT AnuNm-oN, Tcx^c; 760 1 1 • M=-rmn E31 742S5-01 62 CONTRACTORS July 2, 2001 m.r. Tom Shaw Phillip Swagger Associates 7557 Rarnb1cr Road. Suite Dallas, Tx. 75231-2302 Re; Grapevine Public Library - RFF #6 Listed below you will find the cost for completing the work as described on RFP #0. Item *I - Plumbing $ 909.00 Rcmkwo & Replace Ceiling Tilc& & Clean -Up 100.00 Insurance 5.00 Profit & OvcTbcad 101.00 Total $_ Ij 15-00 Item V 2 Plumbing $ 3,656.00 Rcrnovc & Replace Cciling Tilcs & Clean -Up 10,00 Roofuir, 400 Insurance .00 Profit & C)vcrhcad 417.00 Total S4,590,00 This price excludes overtime. If you have any qucstions or need more inibrmatiom please fccl free to contact mc (u; (817)265-9162 Very 'fruty, R obc rt J.'furnian cc,. Bob Price/ City of Grapevine AN CGUAL OPPORTUNITY EMPLOYEEM Received Jul -02-2001 03-25pm From -817 27A 2972 To -CITY OF GRAPEVINE Page 002 G1 - July 24, 2001 Mr. Tom Shaw Phillip Swagger Associates 7557 Rambler Road, Suite 670 Dallas,Texas 75231-2302 Re: Grapevine Public Library - Revised Pricing RFP # 6 Listed below you will find the cost for completing the 2 post Hydrants on the roof as discussed. Plumbing Insurance Profit & Overhead $ 2,980.00 10.00 299.00 Total S 3.289.00 If you have any questions or need more information, please feel free to contact me. Very Truly, Robert J. Turman Jr. President T. W. FOSTER INC. 1 BOCK INDUSTRIAL COURT • ARLINGTON, TEXAS 76011 *Mm oe17-2B5-91 62 CONTRACTORS June 29, 2001 Mr. Bob Price City of Grapevine 501 Shady Brook Drive Grapevine, Texas 76051 Re: Grapevine Public Library Proposed Change Order # 7 - Revised Item H Dear Mr. Price, Below is the price for providing labor and materials for relocation and installation of electrical devices including doorbell, isolated ground quad receptacle in computer room, 50A circuit to stove, fixture in electrical room and Room 114 switch: Electrical General Liability Umbrella Liability Overhead & Profit 10% Total If you have any questions, please feel free to contact me. Thank You, Mary Sypinski CC: David Booher Torn Shaw $ 1,058.00 1.68 2.88 106.26 $ 1,168.82 AN EQUAL OPPORTUNITY FMPI nV;=M T. W . FOSTER 1 N C . 1606 iNo usTRiAL CouRT • ARLINGTON, TExAs 7601 1 + METRO 61 '7-265-21 62 CONTRACTORS June 29, 2001 Mr. Bob Price City of Grapevine 501 Shady`Brook Drive Grapevine, Texas 76051 Re: Grapevine Public Library Proposed Change Order # 7 - Revised Item I Dear Mr. Price, Below is the price for providing labor and materials to install marble thresholds; plastic explosion -proof lens covers for Teen Zone lower lights; 2 checkpoint cabinets; floor tile for Friends closet; corner guards and doors for Program Room: Marble Thresholds (letter dated 6-12) 4 @ $ 85.00 Plastic Lens Cover (letter dated 6-12) 12 @ $ 10.00 Check Point Cabinets (letter dated 6-20) Floor Tile For Friends Closet (letter dated 6-20) 6 - Corner Guards (letter dated 6-20) 2 - Doors For Program Room (letter 6-20) General Liability Umbrella Liability Overhead & Profit TO% Total If you have any questions, please feel free to contact me. Thank You, rn 0)'j Mary Sypinski CC: David Booher Tom Shaw $ 340.00 120.00 750.00 393.75 376.70 464.00 2.01 6.65 245.31 $ 2,698.42 AN EQUAL OPPORTUNITY EMPLOYER �A ,T%A/F T. W . FOSTER t N C . 1 606 INOUSTRIAL COURT • ARUNMMN, TExas 7601 '1 • Myo 817-265- 3162 CONTRACTORS June 92, 2001 Bob Price City of Grapevine Grapevine, Tx 76059 RE. Grapevine Public Library Dear Mr. Price, Below is the price for the Marble Thresholds and plastic lens covers for lower lights Marble threshold 4 @$ 85 $340.00 Plastic Len covers 92 @ $90 $920.00 Bonds 25.00 Total $485.00 If you have any questions or need more information please call me. Thank You, Jim Butler ' P ject Manager T . Poster, Inc. 4 • June 12, 2001 Bob Price City of Grapevine Grapevine, Texas 76051 \3// 1606 INDUSTRIAL COURT • ARLINGTON, TExAs 7601 1 9 N/lETRo 617-265-9162 RE: Grapevine Public Library Dear Mr. Price, Below is the price for the extention of the 80ft glass wall Glass Wall $446.00 Liability Insurance $0.71 Umbrella Insurance $0.76 Builder Risk Insurance $0.24 Bonding $25.00 Subtotal $472.71 10% OHIP Total $519.98 If you have any questions or need more information please call me. Thank im Butler 'roject Manager *.W Foster, Inc. AN EQUAL OPPORTUNITY EMPLOYER ri ,°Tvw T. W. FOSTER INC. CONTRACTORS June 12, 2001 Bob Price City of Grapevine Grapevine, Texas 76051 RE: Grapevine Public Library Dear Mr. Price, 1606 (Nouse AL CouF:rr • ARuNai , N, TExAs 7601 1 • METRo 617-265-9162 Below is the price for the extra plants instead of hydro mulch on sloped hill Purple Winter Creeper 4142.00 x.63 Jute netting and staples 82.00 x 2 Labor 6 men x 10.00 x 6 hr. Spray Mulch Labor on Mulch and netting Landscaper profit and overhead Credit for hydro mulch Liability Insurance Umbrella Insurance Builder Risk Insurance Bonding Subtotal 10% OMP Total - $2,609.46 $164.00 $360.00 $150.00 $200.00 503.32 -$128.00 $6.13 $6.44 $2.00 $125.00 $3,998.35 1399.84 $4,398.19 If you have any questions or need more information please call me. Thank You, T. W.Jedster, Inc. AN ECUAL OPPORTUNITY EMPLOYER