ENGINEERING SERVICES CONTRACT — BASS PRO DRIVE
City Council consider awarding an Engineering Services Contract to TranSystems,
Corporation Consultants for the design of the Bass Pro Drive Reconstruction Project in
an amount not to exceed $ 142,600.00, authorize staff to execute said contract, and
take any necessary action.
FUNDING SOURCE:
Funds are available as follows:
Funding Source
Account
Amount
Award
Percent
95 GO Bonds
178-78348-008
$232,212.50
$142,600
15.9%
96 GO Interest
178-78348-009
$397,000.00
27.2%
99 GO Interest
178-78110-010
$355,000.00
24.4%
00 GO Interest
178-78106-011
$315,787.50
21.7%
Peripheral Street Fees
178-21543
$25,687.53
1.8%
Fellowship Church
$130,800.00
9.0%
TOTAL
$1,456,487.53
$142,600
100%
Budget
Amount
Award
Percent
Engineering
$142,600.00
$142,600
9.8%
Surveying
$14,985.00
1.0%
Construction
$1,100,000.00
75.5%
Contingency
$198,902.53
13.7%
TOTAL
$1,456,487.53
$142,600
100%
BACKGROUND:
The City of Coppell is currently in the process of designing the widening of Bethel Road
within their City extending west to our common City limits line. The engineering firm
providing the engineering services to Coppell is TranSystems Corporation Consultants.
Coppell's planned improvements will provide a four lane divided pavement section within
ON their city.
Staff has previously briefed the City Council on the prospects of continuing the
construction of this project into Grapevine, the benefits of utilizing the same engineering
firm that is designing the Coppell improvements, and the desirability of connecting
Coppell with Bass Pro Drive at SH 121 to complete the improved, multi -lane pavement
section from Coppell to SH 26. Staff has also previously advised Council of the
proposed construction of this project with the Coppell project as one package to take
advantage of better pricing for larger scale projects and to insure a coordinated effort by
the contractor in both cities.
The roadway within Grapevine will be constructed as a four lane concrete pavement
section and will include a multi-chamber box culvert for the Cottonwood Branch crossing
east of the Enchanted Way intersection with Bass Pro Drive.
The three abutting property owners bordering the north side of the 1,800 linear feet of
roadway in Grapevine have agreed to participate in the cost of the project based upon
their respective frontage. Fellowship Church has agreed to provide $ 130,800.00 in
funds. DFW North Limited Partnership and Kendall — Miller Realty Partners have
agreed to a voluntary lien being placed upon their properties in the amounts of
$127,440.00 and $ 54,960.00 respectively. These liens will be due and payable with
N
accrued interest upon the sale of each property or the platting and development of each
property.
The completion of these roadway improvements both in Grapevine and Coppell will
serve as a reliever route for traffic during the construction of the SH 121 / SH 114
Improvements.
Staff recommends approval.
EXHIBIT "A"
SUMMARY OF DESIGN FEE
Revised: 11/19/02
March 6, 2002
Mr. Jerry Hodge
Public Works Director
City of Grapevine
200 South Main Street
Grapevine, TX 76051
RE: Bethel Road
Dear Jerry:
TranSystems appreciates the opportunity to present this proposal for engineering services for the above
referenced project. In preparation of this fee we have visited the site, researched existing records and
coordinated work efforts being performed by our Dallas office for the City of Coppell. The existing road is a
two lane rural section with bar ditches, the proposed section will be either a four lane or six lane divided with
enclosed storm drain. This letter details the services to be performed by TranSystems.
Prepare Base Map
The following tasks have been identified for surveying:
• Topographic survey 200' either side of centerline,
• Tie existing utilities,
• Deed research,
• Property Surveys,
• Right -of -Way (R.O.W.) staking and mapping,
• Tie to City of Grapevine datum,
• Documents for R.O.W. acquisition
$ 19,220.00
Construction Plans & Specifications
The following tasks have been identified to develop final construction drawings:
• Prepare paving plans and specifications,
• Prepare plan & profile sheets for storm drain,
• Prepare general notes,
• Prepare erosion control plans,
• Develop cross sections,
• Prepare a construction estimate and timeline,
• Coordinate with the City of Coppell,
• Design/Review meetings
TranSystems is not including services or fees for the relocation of non -city owned utilities. We will coordinate
our design effort and provide them with plans for their design if required.
$ 66,715.00
Mr. Jerry Hodge
March 6, 2002
Page 2
t �
Bridge Design
The following tasks have been identified to develop complete bridge plans:
• Develop a bridge layout,
• Design per TxDOT standards
• Perform a comparative analysis of standard members,
• Prepare design calculations,
Geotechnical will be provided by the City but could be provided for an additional fee. No retaining walls are
anticipated for this project
$ 18,800.00
Drainage_Designn
The following tasks have been identified to complete the drainage for the proposed improvements:
• Develop hydraulic flows,
• Coordinate with City for analysis of the bridge structure,
• Extend the proposed storm drain from Coppell and provide enclosed storm drain for Cities portion,
• Prepare a drainage area map with flow calculations,
• Prepare plan and profile sheets for enclosed storm drain.
The City will provide modeling of Cottonwood branch. TranSystems will provide flows, cross sections, and a
proposed section for the City to model and coordinate with FEMA.
$ 15,095.00
�Bidding Assistance
The following tasks have been identified to assist in the bidding phase:
• Assist with the pre-bid meeting,
• Prepare addendums if required,
• Prepare bid tabulation,
• Analyze bids for recommendation.
TranSystems will assist the City in bidding the project. TranSystems will provide specifications, a bid tab,
addendums if required and a recommendation for the successful bidder.
$ 5,350.00
Construction Services
The following tasks have been identified to assist during the construction phase:
• Once a month site visits (12),
• Review of the pay estimate,
• Review project submittals,
• Prepare "Record Drawings" from Cities/ Contractor marked up construction plans ( no survey
included),
• Assist City in clarifying contractors questions,
• Conduct final inspection with the City.
C:'.WINDOWYTEMPI bethel-scope-point-rev. DOC
Mr. Jerry Hodge
March 6, 2002
Page 3
TranSystems will assist the City during construction of the project. This fee does not include full time site
inspection. TranSystems will provide the above mentioned services for an estimated time of construction of
12 months.
$ 15,420.00
Reimbursables
The following items have been identified for this project:
• Miscellaneous printing
• Electronic files (Autocad 14)
• Mylar's of record drawings
• Mileage
• Deliveries
$ 2,000.00
TOTAL HOURLY NOT -TO -EXCEED $ 142,600.00
We sincerely appreciate the opportunity to work again with the City of Grapevine. If you have any questions or
require additional information please give me a call.
Sincerely,
TranSystems Corporation Consultants
Joseph C. Masterson, P.E.
Senior Associate