MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: BRUNO RUMBELOW, CITY MANAGER
MEETING DATE: FEBRUARY 5, 2013
SUBJECT: ENGINEERING DESIGN SEVICES CONTRACT—WWTP
FILTER REPLACEMENT PROJECT
RECOMMENDATION:
City Council consider approving an Engineering Design Services Contract with CDM-Smith
in an amount of $156,825 for the Waste Water Treatment Plant Filter Replacement
Project, authorize staff to execute said contract, and take any necessary action.
FUNDING SOURCE:
Funds are available in account 200-48945-534-8-00028 in the amount of $156,825 and
programmed in t ity Funds— Capital Projects.
BACKGROUND:
The Travelling Bridge Sand Filters in both Trains 2 and 3 have exceeded their useful lives
and are in need of complete replacement to continue to meet our effluent permit limits.The
engineering services provided under this contract will address the design of replacement
filters utilizing much newer technology which will serve us for many years to come.
The cost to repair or retrofit the existing filters with its outdated technology is in the same
range as the cost for the newer technology. This new technology will provide the City with
improved effluent results and will provide us the ability to meet future more restrictive
permit requirements.
Staff recommends approval.
RAAGENDA12013102-05-131WWTP Filter Design Contract-CDM-Smith.doc January 15,2013
(4:32:38 PM)
L..ENA #:6
CDM.",,
100 Throckmorton,Suite 600
Fort Worth,TX 76102
tel: 817 332-8727
fax: 817 820-0450
January 28, 2013
Mr.John S. Laster
City of Grapevine
Zoo South Main Street
Grapevine, TX 76051
Subject: Peach Street Wastewater Treatment Plant Filter Improvements-Final Design Phase
Dear Mr. Laster:
CDM Smith is pleased to present our scope of work and fee for engineering services for the
Peach Street Wastewater Treatment Plant Filter Improvements project.
The following revised items are included for the City's review.
Revised Scope for Design, Bid and Construction Phase Services
Attachment A-Engineering Fee for Design, Bid and Construction Phase Services
CDM Smith Inc. is excited to begin work with the City of Grapevine on the filter improvements
at the Peach Street Wastewater Treatment. CDM Smith understands that this work will need to
be executed quickly and efficiently due to the timely nature of the project. Enclosed, please
find one (i) PDF copy for the City's review. Please contact me at (817)332-8727 if you have any
questions.
Sincerely,
Kent W. Riker, P.E.
CDM Smith Inc.
WATER ENVIPONMENT TRANSPORTATION+'ENERGY:EACIMES
L..ENA #:6
City of Grapevine
Filter Peach Street Wastewater Treatment Plant
Scope for Design, Bid and Construction Phase Services
Background
The Peach Street Wastewater Treatment Plant(Plant) utilizes travelling bridge filtration systems as
tertiary treatment for secondary clarifier effluent.The existing travelling bridge filters are in poor
condition and require frequent maintenance.As part of a previous study,alternatives for resolving
the maintenance issues were evaluated and replacing the existing filters with new filters utilizing
cloth media was recommended.Based on the recommendation,the design phase will include
providing a new cloth filtration system.
Scope of Services
The project consists of design and bid phase services for replacement of the existing travelling
bridge filters with new cloth filters installed in the existing chlorine contact basin.
The following paragraphs present the detailed engineering services scope of work and associated
fee for the Filter Improvements at Peach Street Wastewater Treatment Plant.
Project Scope of Work
Task 1 -Design Phase
• Duration:Three Months
• Deliverables: 75%Review Documents
Construction Cost Estimate
Final Documents for Bidding
ENGINEER will develop Construction Documents (plans and specifications) for the purposes of
bidding the project.The following items are included in the project.
Piping modifications to bypass flow around existing travelling bridge filters.
Structural inspection of the existing chlorine contact basin.
New packaged cloth filtration system to be installed in existing chlorine contact basin.
Modifications to chlorine contact basin influent box including addition of gates/valves for
isolation.
® Modifications to chlorine contact basin for installation of new filtration system.
® Modifications to chlorine contact basin sump for draining of water accumulated in the tank
due to rain.
Addition of stairs and platform to access the new cloth filtration system.
Addition of drain piping for draining filter back wash.
® Repairs to sidewalks damaged during piping modifications.
Electrical modifications to provide power to the new packaged filtration system.
® Modifications to SCADA system to include monitoring of the new filtration system.
The following tasks will be included in Task 1:
Pagel . .._ ........
L..ENA #:6
Task 1.1 -Develop Plans
ENGINEER will develop and prepare drawings for use in bidding and constructing the work. The
drawings will include the following engineering disciplines:
& Process/Mechanical
■ CiviI
■ Structural
■ Electrical
■ Instrumentation and Control
ENGINEER will provide five sets of review drawings to the Client at the 75%complete stage,and
will conduct review meetings with City staff. ENGINEER will perform internal technical and QA/QC
reviews.All appropriate comments will be incorporated prior to printing the final documents.
Task 1.2 -Prepare Specifications
ENGINEER will prepare contract documents (specifications)for use in bidding and constructing the
work.Documents will include General and Special Conditions,Bid Proposal Forms,Instructions to
Bidders,Performance Specifications for the Filtration System and all other sections generally
considered to be necessary for solicitation of bids.
Task 1.3 - Opinion of Probable Construction Cost
ENGINEER will prepare an opinion of probable construction cost based on the 75%documents.
Task 1.4-Project Management
ENGINEER will perform project management related duties.Project management duties include
coordinating project tasks,meetings with city staff and obtaining plant process and other
information for use during the project,including progress reporting. It includes internal
management and providing direction to the CDM Smith team on a regular basis,tracking project
costs,the project budget and maintaining project records from project inception to final
completion.Project management duties will also include:
■ Conduct in-house quality control and assurance reviews on all deliverables and coordinate
City reviews.
■ Conduct up to one additional meeting with city staff,utilities management or other
stakeholders during the course of the Final Design Phase,if called upon by the City.
Task 2 -Bidding Phase
• Duration:Bidding Services-Two Months
• Deliverables: Addenda and Recommendation Letter
During the Bidding Phase,the following tasks will be provided.
Task 2.1 - Contract Documents for Bidding Process
ENGINEER will reproduce and distribute contract documents to prospective bidders and vendors
and maintain a log of distribution.ENGINEER will provide 10 sets of half-size drawings and
specifications for distribution.Two full size sets of plans will also be provided.
Task 2.2 -Pre-Bid Meeting
Engineer will attend one pre-bid meeting with prospective bidders.The pre-bid meeting will
include a conference at a location designated by the City and an on-site visit at the Plant.
Task 2.3 - Clarifications to Prospective Bidders
Page2 ...........................
I L..ENA #:6
ENGINEER will provide clarifications and answer questions from prospective bidders during the
bidding phase.If necessary,such clarifications will be included in addenda.
Task 2.4—Bid Recommendation
ENGINEER will attend bid opening,review bids,and assist with recommendations for contract
awards.
TASK - Construction Phase
• Duration:Construction Phase—Eight Months
• Deliverables: Construction Meeting Minutes
Shop Drawing and Submittal Review Comments
During the Construction Phase,the following tasks will be provided.
Task 3.1 —Submittal Review
ENGINEER will perform technical and functional review of all shop drawings and other submittals.
ENGINEER will log-in,track,and distribute submittals to the various disciplines.
Task 3.2 —RFI Review
ENGINEER will respond to all RFIs,as necessary,submitted by the Contractor.ENGINEER will
review and comment on all change order requests and initiate change order requests when
appropriate.
Task 3.3 —Site Visits and Meetings
ENGINEER will attend monthly construction progress meeting with City and Contractor.An
estimate of six construction meetings are included,with one or two persons from ENGINEER's
project team attending.
ENGINEER will make periodic visits to the project site to observe the progress and quality of the
various aspects of the Contractor's work.ENGINEER will participate in substantial completion and
final completion inspections.Up to 10 site visits are included.
Task 3.4—Start-up
ENGINEER will be on-site during equipment Start-up and witness field acceptance test.Up to 2 site
visits are included.
Method of Payment
The method of payment for services rendered by the ENGINEER shall be on a man hour basis as
outlined in Attachment"A",with a not-to-exceed of$156,825. The ENGINEER shall submit
monthly invoices requesting payment based on man hours worked and expenses incurred.
Page 3
ENA #6
---------------------------------------------------------------
10 -0
010 0 to I
figou u 01
�R 1 ED il 0, '! 1 1
a 0 C, a
C3
Lo 4� a r_�Plil 'Ci CNd
_rr, 13�jm co
C'41 �m 1 MIC)
�;;(Ni�2 C6-47' C'j CD C3 M im
co
U)
ll.CD til
Wi: 61 ;.»l 6F.P 69 ep,
0 0 cy
Wc:'! C, C, 0 .-1 C� I
0 Im Cl :01 10.1001
0 'wq&Lo a '21 0! �Olgo '.� 93 0
':lLo Ln lf&:m wa'� Wt M, .0 I I
93
0) � 400- TM 4r, 111"
-------------
C3 ) 0 1® 1001001 1 1. C3 1
C IC31C, o al
61116o 1 �010 a
6o 69-4p�6%if&f&-
ell
40W jlil
H.lf.'-Q[loq lo;r 0 cq N 010 Lo 01
to,
I. . . --------
T
0 010 010 of I lo ol ol cI
je C3 .o 0
o o 'IC3 010 �D
i !C",
C3
cm.-41 0�m 44 Info o of C, �r.Co.0.
cq
ui
101
O.w I oy �o
co M'r
1- -4 �2 to lco `2 CD :2 C>. P_ co -�r
i t 7
0 'q 'r
IN
CL
La lo`olcdo olW C:,:C3 C:)'C) C:)! C3 01 Tr iolo 0 C�.0.Co. to ml T
C'
O]NjN,cojCqjCq I NlCq COICq Nl C,
cm ic3lc3 0 aio of•
I I I I I t
t
C
I
1 101
03
CL
L=1
Cl)
(D r 00.
CL
o 0. La
cm
I
cb
EB!
E
1 C,I L , d)
rml cl I.ai -0 1 0 Q ®r pi.s — D r-. 1.9
C.
44
a.
(0). (E % r,
o 1 IV E
SZ
i
0� E3!ro 0 r
m
io,
cd C r=
I.z
CL
CDI 21 a .-IQ! L3. :3 0,=3 �IrnlvSAl
10.0 0 (D W) WM_E n_ rli iu -si 06 CL V) w 0 to
0 IL C) M�
0 - N Cl Vn V:
!C41N " N! Im 0 cco co