HomeMy WebLinkAboutSTRUCTURAL STEEL - F241078-1531823 - 3-13-2024Our test results and reports are for the exclusive use of the client (and their designated recipients on file in our office) and shall not be reproduced and/or distributed except with
express approval of UES. The use of our name and test results must receive our written approval. Test results and reports apply only to the samples tested and/or observed,
and are not indicative of the qualities of apparently identical or similar specimens.
January 23, 2025
GTIS Acquisitions, LLC
787 Seventh Avenue, 50th Floor
New York, NY 10019
Attention: Kyle Roberson
Re: Field Inspection of Structural Steel
121 Commerce Center Addition (Lot 1)
Grapevine, Texas
UES Report No. F241078-1531823
UES arrived on site to perform a Visual Structural Steel Inspection/Re-Inspection for the above referenced
project. Results of the inspection are as follows:
RE-INSPECTION of OPEN STRUCTURAL STEEL ITEMS NOTED ON REPORT F241078/1485293
(10/28/2024) AND REPORT F241078/1528313 (1/16/2025)
I *NOTE(1): Re-inspected NOTE(4) from report 1528313 (1/16/25) and NOTE(4) from report
1485293 (10/28/24) - referencing the deck support angles at the expansion joints in lines 7/A,
7/F, 13/A and 13/F. In lines F/7 and F/13, the welding contractor slotted the holes in the deck
edge angle with a torch and the angles and anchor bolts at these locations are now in general
compliance with the contract drawings. In lines 13/A and 13/F, the angles are installed vertical
leg up. The anchor bolts for the deck support angle are covered over with roof material and
UES cannot confirm that the anchor bolts for the edge angle are installed in slotted holes. See
details 216/S5.01 and 217/S5.01. Refer to EOR
II *NOTE(2): Re-inspected NOTE(5) from report 1528313, NOTE(5) from report 1485393, item 1(C)
from the report dated 10/18/24, and item 1(C) from report dated 10/14/24 – referencing the joist
seat to precast panel at panel joint welded connection at panels P34 & P35. The welding
contractor has installed (2) ¾” diameter anchors on the non-welded side. Per detail 206/S5.01
– anchors should be 1” diameter. Will require EOR approval on the use of smaller diameter
anchors.
III NOTE(6): The A325 bolted connections, diagonal brace welded connections, column anchor bolt
connections, beam to panel connections, and joist girder to beam connections (sliding side and fixed
side) at the expansion joints in lines 7 and 13 were inspected per the contract drawings on 1/16/25.
Non-compliant issues found during the inspection, and noted by NOTE(6) on report 1528313, are as
follows:
In line 7 – the bolted connections for the joist girder to columns connections on the sliding
side have not been tack welded as per detail. See detail 227/S502 – note (7). This issue was re-
inspected on 1/23/2025 and found to be compliant.
*The column anchor bolt connections are not ready for inspection. Remedial work on
anchor bolt connections that are below flush nut needs to be completed, and the fix used
needs to be approved by the EOR. The welding contractor used ELCONE nuts to correct the
below flush nut anchor bolt connections but they also torch cut oversized holes in the column
baseplates where the below flush nut anchor bolt connections occurred. See details 104/S4.01
and 20/S0.04. Issues regarding the column anchor bolt connections described by NOTE(6) on
report 1528313 remain open.
Our test results and reports are for the exclusive use of the client (and their designated recipients on file in our office) and shall not be reproduced and/or distributed except with
express approval of UES. The use of our name and test results must receive our written approval. Test results and reports apply only to the samples tested and/or observed,
and are not indicative of the qualities of apparently identical or similar specimens.
IV StoreFront/Canopy Steel – Northwest, Northeast, and West – sheets S2.03 & S5.02
A Re-inspected item 1(A) from report 1528313 - referencing the canopy framing welded
connections. It was noted during today’s inspection that the (6”x4”) angle to precast
panel embed welded connections have not been welded out as per details 1 & 2 on
sheet E2004 Connections are to be welded all the way around with ¼” fillet welds.
Additionally, the angle to column connections were to be bolted with ½” diameter
A307 thru-bolts. As built - the angles have been welded to the columns in lieu of
bolting. See details 1 & 2 on sheet E2004 and referenced detail 233/S5.02. Field
modifications for the angle to column connections will require EOR approval and the
missing welds for the angle precast panel connections need to be added and
inspected. The noted damage/gouging caused to the HSS columns for the West
Canopy – lines A & 9 to 11 – where the HSS(12”x6”) beams (HI & LOW) were cut free
and moved to a different elevation - appears to have been addressed.
*Discrepancies, if any, are noted above in bold.
INSPECTOR:
Chris Lalic
CWI#16010691
We are pleased to be of service on this project and if you have any questions, please contact our office.
Sincerely,
UES Professional Solutions 44, LLC
(Formerly Alpha Testing)
Ronnie Yeoman
Project Manager