HomeMy WebLinkAboutItem 12 - Aerial Crossing Big Bear Creek MEMO TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: BRUNO RUMBELOW, CITY MANAGER
MEETING DATE: JULY 18, 2017
SUBJECT: EMERGENCY REPAIRS TO AERIAL SANITARY SEWER
CROSSING BIG BEAR CREEK RESOLUTION APPROVING
CONTRACT AND ADOPT APPROPRIATION ORDINANCE
RECOMMENDATION
City Council consider adopting a resolution declaring an emergency and ratifying the City
Staff's contracting with Brinkley & Barfield, Inc., Wright Construction Company, and HVJ
Associates Geotechnical Services, appropriate funding by ordinance in an amount not to
exceed $150,000 for emergency design and repairs to aerial sanitary sewer crossing over
Big Bear Creek, authorize the City Manager or his designee to execute said contracts and
take any necessary action.
FUNDING:
Funds will be available in the un-appropriated Utility Fund Balance upon approval of the
attached appropriation ordinance.
BACKGROUND:
On the morning of Monday, June 19, Utilities Staff discovered that a 33 year old aerial
sanitary sewer crossing over Big Bear Creek, north of Western Oaks Drive, had been
washed away during an intense rain event. Because it was an emergency, City staff
immediately mobilized to set up a bypass pumping operation in Western Oaks Drive to
another sanitary sewer line, which required closure of two lanes of Western Oaks Drive.
Two way traffic along Western Oaks Drive continues. Staff initiated the necessary
contracts to make repairs that could not be done internally by Staff. The following have
been completed or are in process:
• Brinkley & Barfield has developed a preliminary design awaiting geotechnical data
to finalize pier depths.
• Wright Construction will remove existing damaged piers, pipe and construct a
temporary access road from the north to the south side of the creek. The pier driller
will access site once final design is completed.
• Wright Construction will install and connect new crossing after piers and cap are
placed and cured.
• A proposal from GWC Engineering will be presented at a future Council meeting to
provide design of creek stabilization protection of the north and south bank for the
newly placed piers.
It was important to begin the planning and design process for the repair of the aerial
crossing over Big Bear Creek and re-establish this gravity main as quickly as possible. The
recent rains have slowed the progress to get necessary geotechnical data, but staff
anticipates having Wright Construction and the pier driller in place the week of July 24.
Wright Construction Company has the heavy equipment and experienced crews to respond
to these types of emergencies and provide us a very valuable resource during these times.
Staff recommends approval.
SD/JR
RESOLUTION NO. 2017-063
A RESOLUTION OF THE CITY OF GRAPEVINE CITY
COUNCIL FINDING AND DECLARING AN EMERGENCY TO
PERFORM THE NECESSARY REPAIR CONSTRUCTION
WORK TO THE BEAR CREEK SANITARY SEWER AERIAL
CROSSING; AUTHORIZING EXPENDITURES FOR THE
PERFORMANCE OF SAID WORK; RATIFYING CITY
STAFF'S AWARDING OF CONTRACT FOR SAID WORK
AND DECLARING AN EFFECTIVE DATE
WHEREAS, on the morning of June 19, 2017, the City Staff discovered that a 33
year old aerial sanitary sewer crossing that serves portions of south Grapevine had been
washed away after a morning rain event; and
WHEREAS, said aerial crossing was located in the Big Bear Creek watershed, a
tributary of the Elm Fork of the Trinity River; and
WHEREAS, said damaged crossing resulted in the uncontrolled discharge of
untreated wastewater; and
WHEREAS, City staff mobilized its field crews and equipment to bypass pump the
untreated wastewater to an adjacent sanitary sewer main served by another aerial crossing
in Big Bear Creek; and
WHEREAS, City staff concluded that additional personnel experienced in the type
of repair needed for this replacement with equipment of sufficient size and numbers were
needed from an outside source; and
WHEREAS, City staff contacted Wright Construction Company for this specialized
repair work and Wright Construction Company was able to begin mobilizing forces in
response to planning efforts to the City's request in a prompt manner; and
WHEREAS, City staff contacted Brinkley and Barfield, Inc. for the planning,
response, and design of a new crossing to include casing pipe to span the creek where no
piers would be within the Big Bear Creek bed; and
WHEREAS, City staff contacted HVJ Associates for the specialized work to perform
necessary coring of the soil to allow the engineer to finalize depth of the piers; and
WHEREAS, the prompt responses and planning of Wright Construction, Brinkley
and Barfield, Inc. and HJV Associates have resulted in a significant reduction in the time to
plan and complete the repair; and
WHEREAS, this emergency obligated the City to complete the repair work in the
most efficient manner possible; and
WHEREAS, the City Council deems the adoption of this resolution to be in the best
interests of the health, safety, and welfare of the public.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
GRAPEVINE, TEXAS:
Section 1. That all matters stated hereinabove are found to be true and correct
and are incorporated herein by reference as if copied in their entirety.
Section 2. The City Council finds and concludes that an emergency existed that
required the immediate appropriation of funds to preserve the property of the City, to
protect the public health and safety of the City's residents and to preserve the safety of the
City and its citizens; and,
Section 3. The City Council finds and concludes that the citizens are best served
by the City completing the repair work through a contract with Wright Construction
Company, and for the retention of related professional services, without the necessity of
accepting additional competitive bids pursuant to Chapter 252, Texas Local Government
Code.
Section 4. The City Council approves and ratifies the City Staff's decision to
contract with Wright Construction Company for emergency repair work on the Big Bear
Creek aerial crossing. The City Council further approves and ratifies the City Staff's
decision to contract Brinkley & Barfield, Inc. and HVJ Associates for professional services
related to the emergency repair work on the Big Bear Creek aerial crossing. These
approvals are deemed necessary as a result of unforeseen damage to the aerial crossing
and the need to preserve and protect the public health and safety of the City's residents.
Section 5. That the City Manager, or his designee, is authorized and directed to
enter into agreements for the repair work with each designated company in a total amount
not to exceed $150,000.00.
Section 6. That this resolution shall take effect from and after the date of its
passage.
PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF
GRAPEVINE, TEXAS on this the 18th day of July, 2017.
Resolution No. 2017-063 2
APPROVED:
William D. Tate
Mayor
ATTEST:
Tara Brooks
City Secretary
APPROVED AS TO FORM:
John F. Boyle, Jr.
City Attorney
Resolution No. 2017-063 3
1
■
ORDINANCE NO. 2017-042
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF
GRAPEVINE, TEXAS; APPROPRIATING $150,000.00
FROM THE UNAPPROPRIATED UTILITY FUND BALANCE
FOR DESIGN AND REPAIRS TO THE AERIAL SANITARY
SEWER CROSSING OVER BIG BEAR CREEK;
DECLARING AN EMERGENCY AND PROVIDING AN
EFFECTIVE DATE
WHEREAS, the City supports the design and repairs to the aerial sanitary sewer
crossing over Big Bear Creek with Brinkley and Barfield, Inc., Wright Construction
Company, and HVJ Associates Geotechnical Services; and
WHEREAS, funding of$150,000.00 is available in the unappropriated Utility Fund;
and
WHEREAS, all constitutional and statutory prerequisites for the approval of this
ordinance have been met, including but not limited to the Open Meetings Act; and
WHEREAS, the City Council deems the adoption of this ordinance is in the best
interests of the health, safety, and welfare of the public.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY
OF GRAPEVINE, TEXAS:
Section 1. That all matters stated herein above are true and correct and are
incorporated herein by reference, as if copied in their entirety.
Section 2. That the City Council hereby approves the use of funds from the Utility
Fund.
Section 3. That the City Council hereby authorizes the appropriation of
$150,000.00 from the available Utility Fund Balance.
Section 4. The fact that the present ordinances and regulations of the City of
Grapevine, Texas are inadequate to properly safeguard the health, safety, morals, peace
and general welfare of the public creates an emergency which requires that this ordinance
become effective from and after the date of its passage, and it is accordingly so ordained.
Section 5. That this ordinance shall take effect immediately upon passage by the
City Council of the City of Grapevine, Texas.
PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF
GRAPEVINE, TEXAS on this the 18th day of July, 2017.
APPROVED:
William D. Tate
Mayor
ATTEST:
Tara Brooks
City Secretary
APPROVED AS TO FORM:
John F. Boyle, Jr.
City Attorney
Ordinance No. 2017-042 2