HomeMy WebLinkAboutTerracon - 5/14/2018CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0241
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 05/24/18 Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Material Information Sample Information
Specified Strength: 4,000 psi @ 28 days
Mix ID: 9211
Supplier: Argos
Batch Time: 1405 Plant: 123
Truck No.: 1736 Ticket No.: 12328242
Field Test Data
Test
Result Specification
Slump (in):
7 6-8
Air Content (%):
2.0 0-3
Concrete Temp. (F):
85 45-95
Ambient Temp. (F):
88
Plastic Unit Wt. (pcf):
149.2
Yield (Cu. Yds.):
44.9
Laboratory Test Data
Set Specimen Avg Diam.
No. ID
(in)
1 A
4.00
1 B
4.00
1 C
4.00
1 D
4.00
1 E
05/15/18
Initial Cure: Outside
7
Comments:
Samples Made By: Terracon
Sample Date:
Sampled By:
Weather Conditions:
Accumulative Yards:
Placement Method:
Water Added Before (gal):
Water Added After (gal):
Sample Location:
Placement Location:
Age at Maximum
Area
Date
Date
Test
Load
(sq in)
Received
Tested
(days)
(lbs)
12.57
05/15/18
05/21/18
7
44,090
12.57
05/15/18
06/11/18
28
12.57
05/15/18
06/11/18
28
12.57
05/15/18
06/11/18
28
05/15/18
Hold
Final Cure: Moist Room
05/14/18 Sample Time: 1500
Daniel Blocker
Clear
8 Batch Size (cy): 8
Bucket
Pier, Grid Line P8/16
Drilled Piers, see report
95181011.0240
Compressive
Strength Fracture Tested
(psi) Type By
3,510 2
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Daniel Blocker
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list. Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0241
Service Date: 05/14/18
Report Date: 05/24/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
DRILLED PIER OBSERVATION REPORT
Report Number: 95181011.0240
Irerracon
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 06/06/18 Fort Worth, TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Proiect Number: 95181011
On this date, a Terracon technician arrived at the above referenced jobsite as scheduled for Drilled Pier Observation. See attached sheet
for recorded data.
NOTE: Elevation data provided by others or taken from plans.
Services: Drilled Pier Observation
Terracon Rep.: Daniel Blocker
Reported To:
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
�,Tuipa
Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
sC0001, 10-16-13, Rev.10 Page 1 of 1
DRILLED PIER OBSERVATION
Report Number: 95181011.0240
Service Date: May 14, 2018
Client: Brooks Hospitality Consulting Corp
Attn: Mark Brooks
206 Oldenwood Ct
Colleyville, TX 76034
Driller: CMG
1 rerracon
2501 E. Loop 820 North
Fort Worth, Texas 76118
817-268-8600 Reg No: F-3272
Project:
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project No.: 95181011
Technician: Dan Blocker
Pier Identification
P8/16
Pier Diameter (in.)
48
Top of Ground Elevation (ft.)
630.65
Top of Pier Elevation (ft.)
631.08
Depth to Bearing Stratum from Ground (ft.)
37.0
Depth of Pier from Ground (ft.)
63.9
Required Penetration (ft.)
26.0
Actual Penetration (ft.)
26.9
Depth from Top of Concrete (ft.)
64.5
Condition of Bottom (wet or dry)
Dry
Plumb Within Tolerance (yes or no)
Yes
Casing Diameter (in.)
50
Cased Depth (ft.)
37.0
Number of Vertical Bars (ea.)
16
Reinforcing Bar Size (#)
10
Length of Vertical Bars (ft.)
67.0
Time Drilling was Completed
3:00 PM
Time Concrete was Placed
5:30 PM
Casing stuck into ground had to cut at top of concrete.
Page 1 of 1
Distribution Page
Report Number: 95181011.0240
Service Date: 05/14/18
Report Date: 06/06/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
REINFORCING STEEL OBSERVATIONS REPORT
Report Number: 95181011.0246
Irerracon
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 05/17/18 Revision 1 - Fort Worth, TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
PROJECT DATA
Drawings Utilized: Structural Sheets S3.01
Locations/Items Observed: Basement Floor P4 -P7/15-16
Test Method: Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
Placing Drawings
Approved
X
Bar Length and Shape
X
Column Tie Spacing & Type
Bar Size
X
Proper Bar Placement
X
Stirrup Spacing & Type
X
Bar Grade
X
Properly Tied
X
Welded Splices
Rebar Clean
X
Dowel Bars in Place
X
Mechanical Splices
Trash & Debris Removed
X
Proper Ber Supports
X
Lapped Splices
X
Number of Bars
X
Proper Cover/Clearance
X
Discrepancies/Comments:
Services: Observation of Reinforcing Steel Placement
Terracon Rep.: Daniel Blocker
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
John, Tupa
Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 5-5-10, Rev.7 Page 1 of 1
Distribution Page
Report Number: 95181011.0246
Service Date: 05/14/18
Report Date: 05/17/18 Revision 1 -
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
REINFORCING STEEL OBSERVATIONS REPORT
Report Number: 95181011.0246
Irerracon
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 05/17/18 Fort Worth, TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
PROJECT DATA
Drawings Utilized: Structural Sheets S3.01
Locations/Items Observed: Basement Floor P4 -P7/15-16
Test Method: Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
Placing Drawings
Approved
X
Bar Length and Shape
X
Column Tie Spacing & Type
Bar Size
X
Proper Bar Placement
X
Stirrup Spacing & Type
X
Bar Grade
X
Properly Tied
X
Welded Splices
Rebar Clean
X
Dowel Bars in Place
X
Mechanical Splices
Trash & Debris Removed
X
Proper Ber Supports
X
Lapped Splices
X
Number of Bars
X
Proper Cover/Clearance
X
Discrepancies/Comments:
Services: Observation of Reinforcing Steel Placement
Terracon Rep.: Daniel Blocker
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
J Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 5-5-10, Rev.7 Page 1 of 1
Distribution Page
Report Number: 95181011.0246
Service Date: 05/14/18
Report Date: 05/17/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
FIELD DENSITY TEST REPORT Irerracon
Report Number: 95181011.0242
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 05/15/18 Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Material Information Lab Test Data Project Requirements
Mat.
No.
I
Proctor
Ref. No.
95181011.0006
Classification and Description
Dark Reddish Brown Sandy Clay
Laboratory
Test Method
ASTM D698
Optimum
Water
Max. Lab
Water
Content
Density
Content Compaction
(%)
(pcf)
(%) (%)
18.1
106.4
Opt. +4 93-98
Field Test Data
Probe
Wet
Water
Water
Dry
Percent
Test
Lift /
Mat.
Depth
Density
Content
Content
Density
Compaction
No.
Test Location
Elev.
No.
(in)
(pcf)
(pcf)
(%)
(pcf)
(%)
Grade Beam
60
See Attachment Test #1
F.G.
1
8
122.6
22.3
22.2
100.3
94
61
See Attachment Test #2
F.G.
1
8
127.7
23.9
23.0
103.8
98
62
See Attachment Test #3
F.G.
1
8
126.1
24.8
24.5
101.3
95
63
See Attachment Test #4
F.G.
1
8
128.3
25.5
24.8
102.8
97
64
See Attachment Test #5
F.G.
1
8
123.7
22.9
22.7
100.8
95
Datum: BackFill - Moisture Condition
Std. Cut. M:2238 Std. Cut. D: 652
S/N:
31150 Make: Troxler
Model:
3430
Last Cal. Date:
04/28/2017
Comments: Test and/or retest results on this report meet project requirements as noted above.
Services: Perform in-place density and moisture content tests to determine degree of compaction and material moisture
condition (ASTM D-6938).
Terracon Rep.: Carlos Vela
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list. Reviewed By:
(V'to-
Senior Project Manager
Test Methods: ASTM D6938
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cRoo07, 11-16-12, Rev.7 Page 1 of 1
FIELD DENSITY TESTING REPORT
Irerracon
Report Number: 95181011.0242
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 05/15/18 Fort Worth, TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
I Fr
-r
.16
Yd
p f_J
I.J k'
I JL .. _
i
IF
I L •�.
i
1 nom`_ 3 -
- -.1,
A
Services: Perform in-place density and moisture content tests to determine degree of compaction and material moisture condition
(ASTM D-6938).
Terracon Rep.: Carlos Vela
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
J Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
sc0001, 10-16-13, Rev.10 Page 1 of 1
Distribution Page
Report Number: 95181011.0242
Service Date: 05/14/18
Report Date: 05/15/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0241
Service Date: 05/14/18 2501 E Loop 820 N
Report Date: 06/12/18 Revision 1 - 28 -day results Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Material Information
Sample Information
Specified Strength: 4,000
psi @ 28
days
Sample Date:
05/14/18 Sample Time: 1500
Sampled By:
Daniel Blocker
Mix ID: 9211
Weather Conditions:
Clear
Supplier: Argos
Accumulative Yards:
8 Batch Size (cy): 8
Batch Time: 1405
Plant:
123
Placement Method:
Bucket
Truck No.: 1736
Ticket No.:
12328242
Water Added Before (gal):
Field Test Data
Water Added After (gal):
Sample Location:
Pier, Grid Line P8/16
Test
Result
Specification
Placement Location:
Drilled Piers, see report
Slump (in):
7
6-8
95181011.0240
Air Content (%):
2.0
0-3
Concrete Temp. (F):
85
45-95
Ambient Temp. (F):
88
Plastic Unit Wt. (pcf):
149.2
Yield (Cu. Yds.):
44.9
Laboratory Test Data
Age at Maximum
Compressive
Set Specimen Avg Diam. Area
Date
Date Test Load
Strength Fracture Tested
No. ID (in)
(sq in)
Received
Tested (days) (lbs)
(psi) Type By
1 A 4.00
12.57
05/15/18
05/21/18 7 44,090
3,510 2
1 B 4.00
12.57
05/15/18
06/11/18 28 63,420
5,050 4
1 C 4.00
12.57
05/15/18
06/11/18 28 62,180
4,950 5
1 D 4.00
12.57
05/15/18
06/11/18 28 63,870
5,080 4
Average (28 days)
5,030
1 E
05/15/18
Hold
Initial Cure: Outside
Final Cure: Moist Room
Comments: Average compressive strength of 28 day cylinders complies with the specified strength.
Samples Made By: Terracon
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Daniel Blocker
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list. Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0241
Service Date: 05/14/18
Report Date: 06/12/18 Revision 1 - 28 -day results
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600