HomeMy WebLinkAboutTerracon - 6/20/2018CONCRETE SAMPLE PICK-UP REPORT
Report Number: 95181011.0310A
Service Date: 06/20/18
Report Date: 07/02/18
Irerracon
2501 E Loop 820 N
Fort Worth. TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
On June 20, 2018, a representative of Terracon was present at the above referenced project to obtain 1 set(s) of 5 concrete
test cylinders cast on June 19, 2018. The samples were taken back to the Terracon laboratory where they were cured
under general accordance with ASTM C31 and will be reported under separate cover 95181011.0310.
Services:
Terracon Rep.: Ethan Key
Reported To:
Contractor:
Report Distribution:
See attached distribution list.
Reviewed By:
�Mn,
Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cT0001, 9-28-10, Rev.8 Page 1 of 1
Distribution Page
Report Number: 95181011.0310A
Service Date: 06/20/18
Report Date: 07/02/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE SAMPLE PICK-UP REPORT
Report Number: 95181011.0309A
Service Date: 06/20/18
Report Date: 07/02/18
Irerracon
2501 E Loop 820 N
Fort Worth. TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
On June 20, 2018, a representative of Terracon was present at the above referenced project to obtain 1 set(s) of 5 concrete
test cylinders cast on June 19, 2018. The samples were taken back to the Terracon laboratory where they were cured
under general accordance with ASTM C31 and will be reported under separate cover 95181011.0309.
Services:
Terracon Rep.: Ethan Key
Reported To:
Contractor:
Report Distribution:
See attached distribution list.
Reviewed By:
�Mn,
Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cT0001, 9-28-10, Rev.8 Page 1 of 1
Distribution Page
Report Number: 95181011.0309A
Service Date: 06/20/18
Report Date: 07/02/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
REINFORCING STEEL OBSERVATIONS REPORT
Report Number: 95181011.0314
Irerracon
Service Date: 06/20/18 2501 E Loop 820 N
Report Date: 07/02/18 Fort Worth, TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
PROJECT DATA
Drawings Utilized: R00 -9B
Locations/Items Observed: Footing (Gridlines P12 -P13/18, 17.6 -18/P12 -P13)
Test Method: Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
ITEMS OBSERVED
CORRECT
INCORRECT
Placing Drawings
Approved
X
Bar Length and Shape
X
Column Tie Spacing & Type
Bar Size
X
Proper Bar Placement
X
Stirrup Spacing & Type
X
Bar Grade
X
Properly Tied
X
Welded Splices
Rebar Clean
X
Dowel Bars in Place
X
Mechanical Splices
Trash & Debris Removed
X
Proper Ber Supports
X
Lapped Splices
X
Number of Bars
X
Proper Cover/Clearance
X
Discrepancies/Comments:
Discrepancies were addressed prior to concrete placement.
Services: Observation of Reinforcing Steel Placement
Terracon Rep.: Ethan Key
Reported To: David with Manhattan
Contractor:
Report Distribution:
See attached distribution list.
Reviewed By:
�njupa
Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
CT0001, 5-5-10, Rev.7 Page 1 of 1
Distribution Page
Report Number: 95181011.0314
Service Date: 06/20/18
Report Date: 07/02/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0312
Service Date: 06/20/18 2501 E Loop 820 N
Report Date: 07/19/18 Revision 1 - 28 -day results Fort Worth, TX 76118-6978
Task: 817-268-8600 Reg No: F-3272
Client
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Material Information
Specified Strength: 4,000 psi @ 28 days
Mix ID: 1792
Supplier: Argos
Batch Time: 1420 Plant: 123
Truck No.: 5106 Ticket No.: 12329812
Field Test Data
Test
Slump (in):
Air Content (%):
Concrete Temp. (F):
Ambient Temp. (F):
Plastic Unit Wt. (pcf):
Yield (Cu. Yds.):
Laboratory Test Data
Result Specification
43/4 3 -5
0.8 0-3
90
89
148.8
Set
Specimen
Avg Diam.
Area
Date
No.
ID
(in)
(sq in)
Received
1
A
4.00
12.57
06/21/18
1
B
4.00
12.57
06/21/18
1
C
4.00
12.57
06/21/18
1
D
4.00
12.57
06/21/18
Project
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Sample Information
Sample Date:
Sampled By:
Weather Conditions:
Accumulative Yards:
Placement Method:
Water Added Before (gal):
Water Added After (gal):
Sample Location:
Placement Location:
06/20/18 Sample Time:
Ethan Key
Partly Cloudy
9/35 Batch Size (cy):
Bucket & lift
20
Grid Line P12/18
Structural Beams Grid Line
P12 -P 13/18, 17.6 -18/P12 -P13
1510
1 E 06/21/18 Hold
Initial Cure: Outside Final Cure: Moist Room
Comments: Average compressive strength of 28 day cylinders complies with the specified strength.
Samples Made By: Terracon
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Ethan Key
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
Cx000t, 11-16-12, xev.6 Page 1 of 1
Age at
Maximum
Compressive
Date
Test
Load
Strength
Fracture Tested
Tested
(days)
(lbs)
(psi)
Type By
06/27/18
7
50,500
4,020
4
07/18/18
28
71,270
5,670
4
07/18/18
28
65,870
5,240
5
07/18/18
28
67,380
5,360
4
Average
(28 days)
5,430
1 E 06/21/18 Hold
Initial Cure: Outside Final Cure: Moist Room
Comments: Average compressive strength of 28 day cylinders complies with the specified strength.
Samples Made By: Terracon
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Ethan Key
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
Cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0312
Service Date: 06/20/18
Report Date: 07/19/18 Revision 1 - 28 -day results
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0312
Service Date: 06/20/18 2501 E Loop 820 N
Report Date: 06/29/18 Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Material Information Sample Information
Specified Strength: 4,000 psi @ 28 days
Mix ID: 1792
Supplier: Argos
Batch Time: 1420 Plant: 123
Truck No.: 5106 Ticket No.: 12329812
Field Test Data
Test
Slump (in):
Air Content (%):
Concrete Temp. (F):
Ambient Temp. (F):
Plastic Unit Wt. (pcf):
Yield (Cu. Yds.):
Laboratory Test Data
Set Specimen Avg Diam.
Result Specification
43/4 3 -5
0.8 0-3
90
89
148.8
No. ID
(in)
1 A
4.00
1 B
4.00
1 C
4.00
1 D
4.00
1 E
20
Initial Cure: Outside
7
Comments:
Samples Made By: Terracon
Sample Date:
06/20/18 Sample Time: 1510
Sampled By:
Ethan Key
Weather Conditions:
Partly Cloudy
Accumulative Yards:
9/35 Batch Size (cy): 9
Placement Method:
Bucket & lift
Water Added Before (gal):
20
Water Added After (gal):
7
Sample Location:
Grid Line P12/18
Placement Location:
Structural Beams Grid Line
28
P12 -P 13/18, 17.6 -18/P12 -P13
Age at Maximum
Area
Date
Date
Test
Load
(sq in)
Received
Tested
(days)
(lbs)
12.57
06/21/18
06/27/18
7
50,500
12.57
06/21/18
07/18/18
28
12.57
06/21/18
07/18/18
28
12.57
06/21/18
07/18/18
28
06/21/18
Hold
Final Cure: Moist Room
Compressive
Strength Fracture Tested
(psi) Type By
4,020 4
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Ethan Key
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list. Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
Cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0312
Service Date: 06/20/18
Report Date: 06/29/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0311
Service Date: 06/20/18 2501 E Loop 820 N
Report Date: 07/19/18 Revision 1 - 28 -day results Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Age at
Material Information
Compressive
Sample Information
Area
Specified Strength: 5,000
psi @ 28
days
Sample Date:
06/20/18 Sample Time: 0801
Fracture Tested
No. ID (in)
(sq in)
Sampled By:
Ethan Key
Mix ID: 9727
(lbs)
(psi)
Weather Conditions:
Cloudy
Supplier: Argos
06/21/18
06/27/18
Accumulative Yards:
6 Batch Size (cy): 6
Batch Time: 0708
Plant:
123
Placement Method:
Bucket & lift
Truck No.: 7037
Ticket No.:
12329764
Water Added Before (gal):
15
Field Test Data
12.57
06/21/18
Water Added After (gal):
28
84,330
6,710
4
Sample Location:
Grid Line P6/18
Test
Result
Specification
Placement Location:
Grid Line P6 -P9/18
Slump (in):
5
5-7
Air Content (%):
2.7
3-6
1 E
Concrete Temp. (F):
90
50-95
Hold
Ambient Temp. (F):
76
Initial Cure: Outside
Final Cure: Moist Room
Plastic Unit Wt. (pcf):
149.2
Yield (Cu. Yds.):
Laboratory Test Data
Age at
Maximum
Compressive
Set Specimen Avg Diam.
Area
Date
Date
Test
Load
Strength
Fracture Tested
No. ID (in)
(sq in)
Received
Tested
(days)
(lbs)
(psi)
Type By
1 A 4.00
12.57
06/21/18
06/27/18
7
72,430
5,760
2
1 B 4.00
12.57
06/21/18
07/18/18
28
87,180
6,940
3
1 C 4.00
12.57
06/21/18
07/18/18
28
84,330
6,710
4
1 D 4.00
12.57
06/21/18
07/18/18
28
84,080
6,690
2
Average
(28 days)
6,780
1 E
06/21/18
Hold
Initial Cure: Outside
Final Cure: Moist Room
Comments: Average compressive strength of 28 day cylinders complies with the specified strength.
Samples Made By: Terracon
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Ethan Key
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list. Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0311
Service Date: 06/20/18
Report Date: 07/19/18 Revision 1 - 28 -day results
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0311
Service Date: 06/20/18 2501 E Loop 820 N
Report Date: 06/29/18 Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Material Information Sample Information
Specified Strength: 5,000 psi @ 28 days
Mix ID:
9727
Supplier:
Argos
Batch Time:
0708
Truck No.:
7037
Field Test Data
Test
Slump (in):
Air Content (%):
Concrete Temp. (F):
Ambient Temp. (F):
Plastic Unit Wt. (pcf):
Yield (Cu. Yds.):
Plant: 123
Ticket No.: 12329764
Result
Specification
5
5-7
2.7
3-6
90
50-95
76
4.00
149.2
06/21/18
Laboratory Test Data
Set Specimen Avg Diam.
No. ID
(in)
1 A
4.00
1 B
4.00
1 C
4.00
1 D
4.00
1 E
06/21/18
Initial Cure: Outside
7
Comments:
Sample Date:
Sampled By:
Weather Conditions:
Accumulative Yards:
Placement Method:
Water Added Before (gal):
Water Added After (gal):
Sample Location:
Placement Location:
Age at Maximum
Area
Date
Date
Test
Load
(sq in)
Received
Tested
(days)
(lbs)
12.57
06/21/18
06/27/18
7
72,430
12.57
06/21/18
07/18/18
28
12.57
06/21/18
07/18/18
28
12.57
06/21/18
07/18/18
28
06/21/18
Hold
Final Cure: Moist Room
06/20/18 Sample Time: 0801
Ethan Key
Cloudy
6 Batch Size (cy): 6
Bucket & lift
15
Grid Line P6/18
Grid Line P6 -P9/18
Compressive
Strength Fracture Tested
(psi) Type By
5,760 2
Samples Made By: Terracon
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Ethan Key
Reported To: David with Manhattan
Contractor:
Report Distribution:
See attached distribution list.
Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
Cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0311
Service Date: 06/20/18
Report Date: 06/29/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600