HomeMy WebLinkAboutTerracon - 6/26/2018CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0322
Service Date: 06/26/18 2501 E Loop 820 N
Report Date: 08/03/18 Revision 1 - 28 -day results Fort Worth, TX 76118-6978
Task: 817-268-8600 Reg No: F-3272
Client
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Material Information
Specified Strength: 5,000 psi @ 28 days
Mix ID: D 10000009727
Supplier: Argos
Batch Time: 1340 Plant: 123
Truck No.: 1736 Ticket No.: 12330021
Field Test Data
Test
Slump (in):
Air Content (%):
Concrete Temp. (F):
Ambient Temp. (F):
Plastic Unit Wt. (pcf):
Yield (Cu. Yds.):
Result
Specification
7
5-7
2.7
0-3
92
50-95
88
A
144.9
12.57
Laboratory Test Data
Set
Specimen
Avg Diam.
Area
No.
ID
(in)
(sq in)
1
A
4.00
12.57
1
B
4.00
12.57
1
C
4.00
12.57
1
D
4.00
12.57
Project
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Sample Information
Sample Date:
Sampled By:
Weather Conditions:
Accumulative Yards:
Placement Method:
Water Added Before (gal):
Water Added After (gal):
Sample Location:
Placement Location:
Age at Maximum
Date Date
Test
Load
Received Tested
(days)
(lbs)
07/03/18
7
65,980
07/24/18
28
78,650
07/24/18
28
77,290
07/24/18
28
80,200
Average (28 days)
06/26/18 Sample Time: 1430
Jalil Edwards
Partly Cloudy
9/36 Batch Size (cy): 9
Bucket & lift
0
0
Pier cap gridlines P8 @ 15.2
Grade beam P9 @ 15 Pier cap P8 @
15.2 four columns P6 @ 15.19 & P8,
P9, and P 11 @ 16 Ramp wall P 10.5
toP12 @ 16.3
Compressive
Strength
Fracture Tested
(psi)
Type By
5,250
5
6,260
5
6,150
4
6,380
2
6,260
1 E Hold
Initial Cure: Outside Final Cure: Moist Room
Comments: Average compressive strength of 28 day cylinders complies with the specified strength.
Samples Made By: Terracon
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Jalil Edwards
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list.
Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
Cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0322
Service Date: 06/26/18
Report Date: 08/03/18 Revision 1 - 28 -day results
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon
Report Number: 95181011.0322
Service Date: 06/26/18 2501 E Loop 820 N
Report Date: 07/09/18 Fort Worth, TX 76118-6978
Task: 817-268-8600 Ree No: F-3272
Client Project
Coury Hospitality
Attn: Mark Brooks
7134 S Yale, Ste 400
Tulsa, OK 74136
Grapevine Main Phase 1
815 South Main Street
Grapevine, TX 76051
Project Number: 95181011
Material Information Sample Information
Specified Strength: 5,000 psi @ 28 days
Mix ID: D 10000009727
Supplier: Argos
Batch Time: 1340 Plant: 123
Truck No.: 1736 Ticket No.: 12330021
Field Test Data
Test
Slump (in):
Air Content (%):
Concrete Temp. (F):
Ambient Temp. (F):
Plastic Unit Wt. (pcf):
Yield (Cu. Yds.):
Laboratory Test Data
Set Specimen Avg Diam.
Result Specification
7 5 -7
2.7 0 - 3
92
88
144.9
No. ID
(in)
1 A
4.00
1 B
4.00
1 C
4.00
1 D
4.00
1 E
0
Initial Cure: Outside
0
Comments:
Samples Made By: Terracon
Sample Date:
06/26/18 Sample Time: 1430
Sampled By:
Jalil Edwards
Weather Conditions:
Partly Cloudy
Accumulative Yards:
9/36 Batch Size (cy): 9
Placement Method:
Bucket & lift
Water Added Before (gal):
0
Water Added After (gal):
0
Sample Location:
Pier cap gridlines P8 @ 15.2
Placement Location:
Grade beam P9 @ 15 Pier cap P8 @
28
15.2 four columns P6 @ 15.19 & P8,
12.57
P9, and P 11 @ 16 Ramp wall P 10.5
28
toP12 @ 16.3
Age at Maximum
Area
Date Date
Test
Load
(sq in)
Received Tested
(days)
(lbs)
12.57
07/03/18
7
65,980
12.57
07/24/18
28
12.57
07/24/18
28
12.57
07/24/18
28
Hold
Final Cure: Moist Room
Compressive
Strength Fracture Tested
(psi) Type By
5,250 5
Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength
samples.
Terracon Rep.: Jalil Edwards
Reported To: David with Manhattan
Contractor: Manhattan
Report Distribution:
See attached distribution list. Reviewed By:
Senior Project Manager
Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the
actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cx000t, 11-16-12, xev.6 Page 1 of 1
Distribution Page
Report Number: 95181011.0322
Service Date: 06/26/18
Report Date: 07/09/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery
Irerracon
2501 E Loop 820 N
Fort Worth, TX 76118-6978
817-268-8600
CONCRETE SAMPLE PICK-UP REPORT
Report Number: 95181011.0321A
Service Date: 06/26/18
Report Date: 07/02/18
Irerracon
2501 E Loop 820 N
Fort Worth. TX 76118-6978
817-268-8600 Reg No: F-3272
Client Project
Coury Hospitality Grapevine Main Phase 1
Attn: Mark Brooks 815 South Main Street
7134 S Yale, Ste 400 Grapevine, TX 76051
Tulsa, OK 74136
Project Number: 95181011
On June, 26, 2018, a representative of Terracon was present at the above referenced project to obtain 1 set of 5 concrete
test cylinders cast on June, 25, 2018. The samples were taken back to the Terracon laboratory where they were cured
under general accordance with ASTM C31 and will be reported under separate cover 95181011.0321.
Services:
Terracon Rep.: Jalil Edwards
Reported To:
Contractor:
Report Distribution:
See attached distribution list.
Reviewed By:
�Mn,
Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to
the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials.
cT0001, 9-28-10, Rev.8 Page 1 of 1
Distribution Page
Report Number: 95181011.0321A
Service Date: 06/26/18
Report Date: 07/02/18
Task:
Distribution List
(1) Coury Hospitality, Mark Brooks
(1) AECC Inc, Lee Ledet
(1) ArchiTexas, Michael Karnowski
(1) City of Grapevine TX, Curtis A Bergthold
(1) Construction Management Group of Fair Oaks CA, Blake Cearley
(1) JQ Engineering, Mike Oler
(1) Manhattan Construction Co, Ben Jensen
(1) Manhattan Construction Co, Brad Scheckelhoff
(1) Manhattan Construction Co, Chase Pritchard
(1) Manhattan Construction Co, Daniel Rideau
(1) Manhattan Construction Co, David Saiter
(1) Manhattan Construction Co, Frederick Moore
(1) Manhattan Construction Co, Robert Montgomery