HomeMy WebLinkAboutTerracon - 7/11/2018CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon Report Number: 95181011.0350 Service Date: 07/11/18 2501 E Loop 820 N Report Date: 08/09/18 Revision 1 - 28 -day results Fort Worth, TX 76118-6978 Task: 817-268-8600 Ree No: F-3272 Client Project Coury Hospitality Attn: Mark Brooks 7134 S Yale, Ste 400 Tulsa, OK 74136 Grapevine Main Phase 1 815 South Main Street Grapevine, TX 76051 Project Number: 95181011 Material Information Sample Information Specified Strength: 5,000 psi @ 28 days Sample Date: 07/11/18 Sample Time: 1435 Sampled By: Humberto Portillo Mix ID: 9727 Weather Conditions: Clear Supplier: Argos Accumulative Yards: 10 of 30 Batch Size (cy): 10 Batch Time: 1346 Plant: 123 Placement Method: Direct Discharge Truck No.: 1737 Ticket No.: 12330499 Water Added Before (gal): 0 Water Added After (gal): 0 Field Test Data Sample Location: Parking Garage ColumnsP12/15 Test Result Specification Placement Location: Columns P11/15, P12/15, P13/15, and Slump (in): 63/4 5-7 P13/16.4; Wall from 15-16 Air Content (%): 4.3 3-6 Concrete Temp. (F): 88 50-95 Ambient Temp. (F): 92 Plastic Unit Wt. (pcf): 144.4 Yield (Cu. Yds.): Laboratory Test Data Age at Maximum Compressive Set Specimen Avg Diam. Area Date Date Test Load Strength Fracture Tested No. ID (in) (sq in) Received Tested (days) (lbs) (psi) Type By 1 A 4.00 12.57 07/12/18 07/18/18 7 60,720 4,830 2 1 B 4.00 12.57 07/12/18 08/08/18 28 74,080 5,900 3 1 C 4.00 12.57 07/12/18 08/08/18 28 73,270 5,830 4 1 D 4.00 12.57 07/12/18 08/08/18 28 77,590 6,170 2 Average (28 days) 5,970 1 E 07/12/18 Hold Initial Cure: Outside Final Cure: Moist Room Comments: Average compressive strength of 28 day cylinders complies with the specified strength. Samples Made By: Terracon Services: Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive strength samples. Terracon Rep.: Humberto Portillo Reported To: David with Manhattan Contractor: Manhattan Report Distribution: See attached distribution list. Reviewed By: Senior Project Manager Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231 The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. cx000t, 11-16-12, xev.6 Page 1 of 1 Distribution Page Report Number: 95181011.0350 Service Date: 07/11/18 Report Date: 08/09/18 Revision 1 - 28 -day results Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) Construction Management Group of Fair Oaks CA, Blake Cearley (1) JQ Engineering, Mike Oler (1) Manhattan Construction Co, Ben Jensen (1) Manhattan Construction Co, Brad Scheckelhoff (1) Manhattan Construction Co, Chase Pritchard (1) Manhattan Construction Co, Daniel Rideau (1) Manhattan Construction Co, David Saiter (1) Manhattan Construction Co, Frederick Moore (1) Manhattan Construction Co, Robert Montgomery Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600 CONCRETE COMPRESSIVE STRENGTH TEST REPORT Irerracon Report Number: 95181011.0350 Service Date: 07/11/18 2501 E Loop 820 N Report Date: 07/19/18 Fort Worth, TX 76118-6978 Task: 817-268-8600 Ree No: F-3272 Client Project Coury Hospitality Attn: Mark Brooks 7134 S Yale, Ste 400 Tulsa, OK 74136 Grapevine Main Phase 1 815 South Main Street Grapevine, TX 76051 Project Number: 95181011 Material Information Sample Information Specified Strength: 5,000 psi @ 28 days Mix ID: 9727 Supplier: Argos Batch Time: 1346 Plant: 123 Truck No.: 1737 Ticket No.: 12330499 Field Test Data Test Slump (in): Air Content (%): Concrete Temp. (F): Ambient Temp. (F): Plastic Unit Wt. (pcf): Yield (Cu. Yds.): Laboratory Test Data Set Specimen Avg Diam. Result Specification 63/4 5 -7 4.3 3 - 6 88 92 144.4 No. ID (in) 1 A 4.00 1 B 4.00 1 C 4.00 1 D 4.00 1 E 07/12/18 Initial Cure: Outside 7 Comments: Samples Made By: Terracon Services: Sample Date: Sampled By: Weather Conditions: Accumulative Yards: Placement Method: Water Added Before (gal): Water Added After (gal): Sample Location: Placement Location: Age at Maximum Area Date Date Test Load (sq in) Received Tested (days) (lbs) 12.57 07/12/18 07/18/18 7 60,720 12.57 07/12/18 08/08/18 28 12.57 07/12/18 08/08/18 28 12.57 07/12/18 08/08/18 28 07/12/18 Hold Final Cure: Moist Room Terracon Rep.: Humberto Portillo Reported To: David with Manhattan Contractor: Report Distribution: See attached distribution list. 07/11/18 Sample Time: 1435 Humberto Portillo Clear 10 of 30 Batch Size (cy): 10 Direct Discharge P12/15 Columns P11/15, P12/15, P13/15, and P13/16.4; Wall from 15-16 Compressive Strength Fracture Tested (psi) Type By 4,830 2 Reviewed By: Senior Project Manager Test Methods: ASTM C 31, ASTM C39, ASTM C138, ASTM C143, ASTM C172, ASTM C231, ASTM C1064, ASTM C1231 The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. cx000t, 11-16-12, xev.6 Page 1 of 1 Distribution Page Report Number: 95181011.0350 Service Date: 07/11/18 Report Date: 07/19/18 Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) Construction Management Group of Fair Oaks CA, Blake Cearley (1) JQ Engineering, Mike Oler (1) Manhattan Construction Co, Ben Jensen (1) Manhattan Construction Co, Brad Scheckelhoff (1) Manhattan Construction Co, Chase Pritchard (1) Manhattan Construction Co, Daniel Rideau (1) Manhattan Construction Co, David Saiter (1) Manhattan Construction Co, Frederick Moore (1) Manhattan Construction Co, Robert Montgomery Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600 CANCELLED SERVICE REPORT Report Number: 95181011.0349 Service Date: 07/11/18 Report Date: 07/23/18 Irerracon 2501 E Loop 820 N Fort Worth. TX 76118-6978 817-268-8600 Reg No: F-3272 Client Project Coury Hospitality Grapevine Main Phase 1 Attn: Mark Brooks 815 South Main Street 7134 S Yale, Ste 400 Grapevine, TX 76051 Tulsa, OK 74136 Project Number: 95181011 On 07/18/2018 a representative of Terracon arrived at the above referenced project to perform concrete testing. Upon arrival to the site the technician was notified by David with Manhattan that services had been cancelled due to having issues with the post -tension cables. Services: Terracon Rep.: Humberto Portillo Reported To: David with Manhattan Contractor: Manhattan Report Distribution: See attached distribution list. Reviewed By: �Mn, Senior Project Manager The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. cT0001, 9-28-10, Rev.8 Page 1 of 1 Distribution Page Report Number: 95181011.0349 Service Date: 07/11/18 Report Date: 07/23/18 Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) Construction Management Group of Fair Oaks CA, Blake Cearley (1) JQ Engineering, Mike Oler (1) Manhattan Construction Co, Ben Jensen (1) Manhattan Construction Co, Brad Scheckelhoff (1) Manhattan Construction Co, Chase Pritchard (1) Manhattan Construction Co, Daniel Rideau (1) Manhattan Construction Co, David Saiter (1) Manhattan Construction Co, Frederick Moore (1) Manhattan Construction Co, Robert Montgomery Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600 POST -TENSION OBSERVATIONS REPORT Report Number: 95181011.0348 Irerracon Service Date: 07/11/18 2501 E Loop 820 N Report Date: 07/23/18 Fort Worth, TX 76118-6978 817-268-8600 Reg No: F-3272 Client Project Coury Hospitality Grapevine Main Phase 1 Attn: Mark Brooks 815 South Main Street 7134 S Yale, Ste 400 Grapevine, TX 76051 Tulsa, OK 74136 Project Number: 95181011 PROJECT DATA Drawings Utilized: PTO 1, PT02, PT03, PT04, PT05, PT06, PT07, PT08, R02 -1G, R02 -1R, R02 -1Q, R02 -1K, R02 -1H Locations/Items Observed: Pour 5 Section North of Pour Strip Test Method: Visual Observation REPORT OF OBSERVATION ITEMS OBSERVED CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT Placing DrawingsX Approved Length and Shape X Column Tie Spacing & Type Bar and Cable Size X Proper Placement X Stirrup Spacing & Type X Bar and Cable Grade X Properly Tied X Cables Properly Wrapped Rebar and Cables Clean X Dowel Bars in Place X Mechanical Splices Trash & Debris Removed X Proper Supports X Lapped Splices X Number of Bars and Cables X Proper Cover/Clearance X Proper Drape of Cables X Discrepancies/Comments: Cable U108 and U039 switched at the live end Tendons missing in beam on 15 Line and Tendons U054B and U054C have been placed into the beam past the stairs. Calc. Elongations will also not match due to the issue. Extra "short" tendon added between U043 and U044 at the same starting grid line as U109 T043 live end was not properly attached to the forms. P7/16 Cables were covered in dried concrete from previous pour. T022A and T022B were cut and two new strands were continued. T023A and T023B were not stressed prior to next area being poured. Clearance issues on multiple beams/Girder Services: Terracon Rep.: Adam Wood Reported To: Contractor: Report Distribution: See attached distribution list. Reviewed By: �njupa Senior Project Manager The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. R940004, 07-01-12, Rev.0 Page 1 of 1 Distribution Page Report Number: 95181011.0348 Service Date: 07/11/18 Report Date: 07/23/18 Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) Construction Management Group of Fair Oaks CA, Blake Cearley (1) JQ Engineering, Mike Oler (1) Manhattan Construction Co, Ben Jensen (1) Manhattan Construction Co, Brad Scheckelhoff (1) Manhattan Construction Co, Chase Pritchard (1) Manhattan Construction Co, Daniel Rideau (1) Manhattan Construction Co, David Saiter (1) Manhattan Construction Co, Frederick Moore (1) Manhattan Construction Co, Robert Montgomery Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600 POST -TENSION STRESSING REPORT Report Number: 95181011.0347 Irerracon Service Date: 07/11/18 2501 E Loop 820 N Report Date: 07/16/18 Fort Worth, TX 76118-6978 817-268-8600 Reg No: F-3272 Client Project Coury Hospitality Grapevine Main Phase 1 Attn: Mark Brooks 815 South Main Street 7134 S Yale, Ste 400 Grapevine, TX 76051 Tulsa, OK 74136 Proiect Number: 95181011 On this date, a representative of Terracon arrived at the above referenced jobsite as scheduled to observe Post Tension Stressing Operations on Level 2, Pour #4. Please note that tendons highlighted in yellow are outside the tolerance of +/-7%. See attached sheets for recorded data. Services: Terracon Rep.: Adam Wood Reported To: Contractor: Manhattan Report Distribution: See attached distribution list. Reviewed By: �,Tuipa Senior Project Manager The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. sC0001, 10-16-13, Rev.10 Page 1 of 1 MEASURED ELONGATION TENDON MARK CALC ELONG (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) Restress (psi or 7% kips) TOTAL (in.) % (+/-) REMARKS 0001A 7.125 5.75 6.63 5.75 7.62 5.75 -19% 00018 7.125 6.63 #VALUE! 7.62 #VALUE! #VALUE! See Comments 0002 7.125 6.63 #VALUE! 7.62 #VALUE! #VALUE! See Comments 0003A 7.125 6.5 6.63 6.50 7.62 6.5 -9% 00036 7.125 7.25 6.63 7.25 7.62 7.25 2% 0004A 7.125 6.625 6.63 6.63 7.62 6.625 -7% 0004B 7.125 6.625 6.63 6.63 7.62 6.625 -7% 0005 7.125 6 6.63 6.00 7.62 6 -16% 0006A 7.125 7.125 6.63 7.13 7.62 7.125 0% 00066 7.125 6.875 6.63 6.88 7.62 6.875 -4% 0007A 7.125 6.75 6.63 6.75 7.62 6.75 -5% 0007B 7.125 7.25 6.63 7.25 7.62 7.25 2% 0008 7.125 7.125 6.63 7.13 7.62 7.125 0% 0009A 7.125 6.75 6.63 6.75 7.62 6.75 -5% 0009B 7.125 7.375 6.63 7.38 7.62 7.375 4% U010A 7.125 7.125 6.63 7.13 7.62 7.125 0% U01013 7.125 7 6.63 7.00 7.62 7 -2% U011 7.125 6.75 6.63 6.75 7.62 6.75 -5% U012A 7.125 7.125 6.63 7.13 7.62 7.125 0% U012B 7.125 6.75 6.63 6.75 7.62 6.75 -5% U013A 7.125 7.5 6.63 7.50 7.62 7.5 5% U013B 7.125 7.625 6.63 7.63 7.62 7.625 7% U014 7.125 6.375 6.63 6.38 7.62 6.375 -11% U015A 7.125 6.875 6.63 6.88 7.62 6.875 -4% U015B 7.125 7 6.63 7.00 7.62 7 -2% U016A 7.125 6.875 6.63 6.88 7.62 6.875 -4% U016B 7.125 7 6.63 7.00 7.62 7 -2% U017 7.125 7.125 6.63 7.13 7.62 7.125 0% U018 7.125 6.375 6.63 6.38 7.62 6.375 -11% U023A 4.875 4.53 #VALUE! 5.22 #VALUE! #VALUE! See Comments U023B 4.875 4.53 #VALUE! 5.22 #VALUE! #VALUE! See Comments U024 4.875 6.375 4.53 6.38 5.22 6.375 31% U025A 4.875 5.875 4.53 5.88 5.22 5.875 21% U025B 4.875 6.625 4.53 6.63 5.22 6.625 36% U026A 4.875 6 4.53 6.00 5.22 6 23% COMMENTS: Tendons 00016 & 0002 are live end anchors, Tendons U023A & U023B not pulled due to U022 Failure SHEETTITLE: ELONGATION RECORDS Jack #1: MRE001 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR. Jack #1 PSI: 5400 LEVEL/POUR: Level 2, Pour 4 Jack #2 PSI: DATE: 7/11/18 1 STRESS BY: K & A Rebar IVERIFIED BY: Adam Wood PAGE 1 OF 6 MEASURED ELONGATION CALC TENDON ELONG MARK (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) 7% Restress (psi or kips) TOTAL (in.) % (+/-) REMARKS U026B 4.875 5.875 4.53 5.88 5.22 5.875 21% U027A 4.875 6 4.53 6.00 5.22 6 23% U027B 4.875 6.125 4.53 6.13 5.22 6.125 26% U028 4.875 6.375 4.53 6.38 5.22 6.375 31% U029A 4.875 6.125 4.53 6.13 5.22 6.125 26% U029B 4.875 6.125 4.53 6.13 5.22 6.125 26% U030A 4.875 6 4.53 6.00 5.22 6 23% U030B 4.875 6.25 4.53 6.25 5.22 6.25 28% U031A 4.875 5.875 4.53 5.88 5.22 5.875 21% U031B 4.875 6.125 4.53 6.13 5.22 6.125 26% U032 4.875 6.25 4.53 6.25 5.22 6.25 28% U033A 4.875 6.75 4.53 6.75 5.22 6.75 38% U033B 4.875 5.75 4.53 5.75 5.22 5.75 18% U034 4.875 6.375 4.53 6.38 5.22 6.375 31% SHEETTITLE: ELONGATION RECORDS Jack #1: MRE001 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR: Jack #1 PSI: 5400 LEVEL/POUR: Level 2, Pour 4 Jack #2 PSI: DATE: 7/11/18 1 STRESS BY: K & A Rebar IVERIFIED BY: Adam Wood PAGE 2 OF 6 MEASURED ELONGATION CALC TENDON ELONG MARK (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) 7% Restress (psi or kips) TOTAL (in.) % (+/-) REMARKS M011A 4.5 4.25 4.19 4.25 4.82 4.25 -6% M011B 4.5 4.125 4.19 4.13 4.82 4.125 -8% M011C 4.5 4.375 4.19 4.38 4.82 4.375 -3% M011D 4.5 4.125 4.19 4.13 4.82 4.125 -8% M011E 4.5 4.375 4.19 4.38 4.82 4.375 -3% M001F 4.5 4.25 4.19 4.25 4.82 4.25 -6% M011G 4.5 4.25 4.19 4.25 4.82 4.25 -6% M011H 4.5 4.25 4.19 4.25 4.82 4.25 -6% M0111 4.5 41/2 4.19 4.50 4.82 4.5 0% M011J 4.5 4.75 4.19 4.75 4.82 4.75 6% M011K 4.5 4.875 4.19 4.88 4.82 4.875 8% M011L 4.5 4.75 4.19 4.75 4.82 4.75 6% M001M 4.5 5.125 4.19 5.13 4.82 5.125 14% M005A 13 13.25 12.09 13.25 13.91 13.25 2% M005B 13 13.5 12.09 13.50 13.91 13.5 4% M005C 13 13.375 12.09 13.38 13.91 13.375 3% M005D 13 13.125 12.09 13.13 13.91 13.125 1% M005E 13 13 12.09 13.00 13.91 13 0% M005F 13 13.75 12.09 13.75 13.91 13.75 6% M005G 13 14.5 12.09 14.50 13.91 14.5 12% M005H 13 15.25 12.09 15.25 13.91 15.25 17% M0051 13 14.875 12.09 14.88 13.91 14.875 14% M005J 13 14.25 12.09 14.25 13.91 14.25 10% M005K 13 14.5 12.09 14.50 13.91 14.5 12% M005L 13 13.875 12.09 13.88 13.91 13.875 7% M005M 13 14.125 12.09 14.13 13.91 14.125 9% M005N 13 13.5 12.09 13.50 13.91 13.5 4% M0050 13 15.5 12.09 15.50 13.91 15.5 19% M005P 13 12.09 #VALUE! 13.91 #VALUE! #VALUE! See Comments M005Q 13 14.125 12.09 14.13 13.91 14.125 9% COMMENTS: Tendon M005P Broke SHEETTITLE: ELONGATION RECORDS Jack #1: MRE001 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR: Jack #1 PSI: 5400 LEVEL/POUR: Level 2, Pour 4 Jack #2 PSI: DATE: 7/11/18 1 STRESS BY: K & A Rebar IVERIFIED BY: Adam Wood PAGE 3 OF 6 MEASURED ELONGATION TENDON MARK CALC ELONG (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) Restress (psi or 7% kips) TOTAL (in.) % (+/-) REMARKS M102A 4.875 6.125 4.53 6.13 5.22 6.125 26% See comments M102B 4.875 6 4.53 6.00 5.22 6 23% See comments M102C 4.875 6.375 4.53 6.38 5.22 6.375 31% See comments M103D 4.875 6.5 4.53 6.50 5.22 6.5 33% M102E 4.875 6.25 4.53 6.25 5.22 6.25 28% M102F 4.875 6 4.53 6.00 5.22 6 23% M102G 4.875 6 4.53 6.00 5.22 6 23% M006A 13 135/8 12.09 13.63 13.91 13.625 5% M006B 13 13.625 12.09 13.63 13.91 13.625 5% M006C 13 13.5 12.09 13.50 13.91 13.5 4% M006D 13 15.5 12.09 15.50 13.91 15.5 19% M006E 13 13.75 12.09 13.75 13.91 13.75 6% M006F 13 11.625 12.09 11.63 13.91 11.625 -11% M006G 13 14.75 12.09 14.75 13.91 14.75 13% M006H 13 13.625 12.09 13.63 13.91 13.625 5% M0061 13 14.25 12.09 14.25 13.91 14.25 10% M 0061 13 15 12.09 15.00 13.91 15 15% M006K 13 14.25 12.09 14.25 13.91 14.25 10% M006L 13 13.875 12.09 13.88 13.91 13.875 7% M007A 12.375 13 11.51 13.00 13.24 13 5% M007B 12.375 14.125 11.51 14.13 13.24 14.125 14% M007C 12.375 13.5 11.51 13.50 13.24 13.5 9% M007D 12.375 13.5 11.51 13.50 13.24 13.5 9% M007E 12.375 13.125 11.51 13.13 13.24 13.125 6% M007F 12.375 13.375 11.51 13.38 13.24 13.375 8% M007G 12.375 14.125 11.51 14.13 13.24 14.125 14% M007H 12.375 15 11.51 15.00 13.24 15 21% M0071 12.375 14.125 11.51 14.13 13.24 14.125 14% M031A 8.875 9.75 8.25 9.75 9.50 9.75 10% M031B 8.875 10.25 8.25 10.25 9.50 10.25 15% COMMENTS: M102 calculated elongations will not match up due to the pour extending to P5. M102 was also stressed after M011 & the East end of M005 & before the other beams SHEETTITLE: ELONGATION RECORDS Jack #1: MRE001 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR. Jack #1 PSI: 5400 LEVEL/POUR: Level 2, Pour 4 Jack #2 PSI: DATE: 7/11/18 1 STRESS BY: K & A Rebar IVERIFIED BY: Adam Wood PAGE 4 OF 6 MEASURED ELONGATION TENDON MARK CALC ELONG (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) 7% Restress (psi or kips) TOTAL (in.) % (+/-) REMARKS M004A 4.875 4.625 4.53 4.63 5.22 4.625 -5% ALT./MRE004 M004B 4.875 4.5 4.53 4.50 5.22 4.5 -8% ALT./MRE004 M004C 4.875 4.75 4.53 4.75 5.22 4.75 -3% ALT./MRE004 M004D 4.875 4.625 4.53 4.63 5.22 4.625 -5% ALT./MRE004 M004E 4.875 4.625 4.53 4.63 5.22 4.625 -5% M004F 4.875 4.5 4.53 4.50 5.22 4.5 -8% M004G 4.875 4.75 4.53 4.75 5.22 4.75 -3% M004H 4.875 5 4.53 5.00 5.22 5 3% M0041 4.875 43/4 4.53 4.75 5.22 4.75 -3% M004J 4.875 4.625 4.53 4.63 5.22 4.625 -5% M004K 4.875 4.875 4.53 4.88 5.22 4.875 0% M004L 4.875 4 4.53 4.00 5.22 4 -18% M004M 4.875 4.775 4.53 4.78 5.22 4.775 -2% M004N 4.875 5.25 4.53 5.25 5.22 5.25 8% M0040 4.875 4.875 4.53 4.88 5.22 4.875 0% M103A 1.625 1.25 1.51 1.25 1.74 1.25 -23% ALT./MRE004 M103B 1.625 1.25 1.51 1.25 1.74 1.25 -23% ALT./MRE004 M103C 1.625 1.625 1.51 1.63 1.74 1.625 0% ALT./MRE004 M103D 1.625 1.25 1.51 1.25 1.74 1.25 -23% ALT./MRE004 M101A 6 5.5 5.58 5.50 6.42 5.5 -8% ALT./MRE004 M101B 6 5.75 5.58 5.75 6.42 5.75 -4% ALT./MRE004 M101C 6 6.125 5.58 6.13 6.42 6.125 2% ALT./MRE004 M101D 6 5.5 5.58 5.50 6.42 5.5 -8% ALT./MRE004 M101E 6 6.25 5.58 6.25 6.42 6.25 4% ALT./MRE004 M101F 6 6.125 5.58 6.13 6.42 6.125 2% ALT./MRE004 M101G 6 5.625 5.58 5.63 6.42 5.625 -6% ALT./MRE004 M101H 6 5.625 5.58 5.63 6.42 5.625 -6% ALT./MRE004 M1011 6 5.75 5.58 5.75 6.42 5.75 -4% ALT./MRE004 M101J 6 5.75 5.58 5.75 6.42 5.75 -4% ALT./MRE004 M101K 6 6.5 5.58 6.50 6.42 6.5 8% ALT./MRE004 M101L 6 6.5 5.58 6.50 6.42 6.5 8% ALT./MRE004 M101M 6 5.75 5.58 5.75 6.42 5.75 -4% ALT./MRE004 M101N 6 6 5.58 6.00 6.42 6 0% ALT./MRE004 COMMENTS: MRE004 Replacement Jack SHEETTITLE: ELONGATION RECORDS Jack #1: MRE001 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR: Jack #1 PSI: 5400 LEVEL/POUR: Level 2, Pour 4 Jack #2 PSI: DATE: 7/11/18 1 STRESS BY: K & A Rebar IVERIFIED BY: Adam Wood PAGE 5 OF 6 MEASURED ELONGATION CALC TENDON ELONG MARK (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) 7% Restress (psi or kips) TOTAL (in.) % (+/-) REMARKS M1010 6 5.75 5.58 5.75 6.42 5.75 -4% M101P 6 5.625 5.58 5.63 6.42 5.625 -6% M101Q 6 6.25 5.58 6.25 6.42 6.25 4% M101R 6 6.5 5.58 6.50 6.42 6.5 8% M1015 6 5.875 5.58 5.88 6.42 5.875 -2% M101T 6 5.75 5.58 5.75 6.42 5.75 -4% M101U 6 6.25 5.58 6.25 6.42 6.25 4% M101V 6 5.75 5.58 5.75 6.42 5.75 -4% M101W 6 53/8 5.58 5.38 6.42 5.375 -10% M101X 6 5.5 5.58 5.50 6.42 5.5 -8% SHEETTITLE: ELONGATION RECORDS Jack #1: MRE001 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR: Jack #1 PSI: 5400 LEVEL/POUR: Level 2, Pour 4 Jack #2 PSI: DATE: 7/11/18 1 STRESS BY: K & A Rebar IVERIFIED BY: Adam Wood PAGE 6 OF 6 Distribution Page Report Number: 95181011.0347 Service Date: 07/11/18 Report Date: 07/16/18 Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) Construction Management Group of Fair Oaks CA, Blake Cearley (1) JQ Engineering, Mike Oler (1) Manhattan Construction Co, Ben Jensen (1) Manhattan Construction Co, Brad Scheckelhoff (1) Manhattan Construction Co, Chase Pritchard (1) Manhattan Construction Co, Daniel Rideau (1) Manhattan Construction Co, David Saiter (1) Manhattan Construction Co, Frederick Moore (1) Manhattan Construction Co, Robert Montgomery Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600 CONCRETE SAMPLE PICK-UP REPORT Report Number: 95181011.0346A Service Date: 07/11/18 Report Date: 07/13/18 Irerracon 2501 E Loop 820 N Fort Worth. TX 76118-6978 817-268-8600 Reg No: F-3272 Client Project Coury Hospitality Grapevine Main Phase 1 Attn: Mark Brooks 815 South Main Street 7134 S Yale, Ste 400 Grapevine, TX 76051 Tulsa, OK 74136 Project Number: 95181011 On 07/11/2018, a representative of Terracon was present at the above referenced project to obtain 1 set of 5 concrete test cylinders cast on 07/10/2018. The samples were taken back to the Terracon laboratory where they were cured under general accordance with ASTM C31 and will be reported under separate cover 95181011.0346. Services: Terracon Rep.: Humberto Portillo Reported To: David with Manhattan Contractor: Manhattan Report Distribution: See attached distribution list. Reviewed By: �Mn, Senior Project Manager The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. cT0001, 9-28-10, Rev.8 Page 1 of 1 Distribution Page Report Number: 95181011.0346A Service Date: 07/11/18 Report Date: 07/13/18 Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) Construction Management Group of Fair Oaks CA, Blake Cearley (1) JQ Engineering, Mike Oler (1) Manhattan Construction Co, Ben Jensen (1) Manhattan Construction Co, Brad Scheckelhoff (1) Manhattan Construction Co, Chase Pritchard (1) Manhattan Construction Co, Daniel Rideau (1) Manhattan Construction Co, David Saiter (1) Manhattan Construction Co, Frederick Moore (1) Manhattan Construction Co, Robert Montgomery Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600