HomeMy WebLinkAboutFargo Consultants, Inc. - 6/1/2017F'G0 �ICr FARGO CONSULTANTS, INC. DAILY FIELD REPORT Client: JLB Partners, LP Project Name: Grapevine Bluffs Project Location: Grapevine, Texas Service(s) Provided: Structural Steel Observation Service(s) Performed By: BI'I Inspection Services 2324 Fabens Rd. • D-Aas, Texas 75229 Tel 214-352-4100 Fax 214-352-4811 Date Performed: 6/1/2017 FARGO Job No: M16-4962 Respectfully Submitted, Fargo Consultants, Inc. The information and results shown on this report are for the exclusive use of the client and the client's designated recipients on file in our office. Test results are based on data obtained from specific samples tested at particular locations noted and are not indicative of the qualities of apparently identical or similar specimens, composition, performance, etc. The use of our name and test results must receive our written approval. Reports must be reproduced in their entirety. Geotechnical Engineering • Construction Materials Testing • Environmental Services www. dallasfargo. coni BKH INSPECTION SERVICES, LLC. P.O Box 2472 Burleson, Tx 76097 817-726-5456 bkhinsaection(i�utnail.com www.bkh i nspection.com REPORT OF STRUCTURAL STEEL INSPECTION Client: Fargo Consultants, Inc. Project: Grapevine Bluffs- Gra 3c v i Ill:. TX Services: Visual Inspection Drawings Utilized: Locations and Items Inspected: Discrepancies/Comments: Contract Documents. Report No.: Project No.: Date of Service: Purchase Order No.: Page Fitness Center structural steel j4rid lines 1-5 & A-E. SS31534 M16-4962 06-01-2017 3502 1 of 1 I. The Fitness Center structural steel main frame bolted and welded connections at grid lines 1-5 & A-E with the results as follows: A) The beam bolted and welded connections appear to be acceptable per the RFI dated 05-25-2017 and the contract documents. -Compliant B) The beam to column cap plate welded connections appear to be acceptable per the contract documents. -Compliant C) The column to embed plate welded connections appear to be acceptable, with the exception of the column at grid lines 1 & D has been welded on 3 sides only. This item will need an RFI from Engineering. -Non -Compliant II. BKH Inspection Services, LLC has received an RFI dated 05-25-2017 for the main frame bolted and welded connections at Building 1 Leasing Office. This clears item I (B) on report #SS31388 dated 05-24-2017 and item II on report #SS31527 dated 05 -25 -2017. -Compliant A�" Technician/ Inspectors Signature MaA CW I#97041661 BKH Inspection Services, LLC. Limitations. The test results herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality (composition, appearance, performance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control, this document is not a warranty or guaranty of the components inspected, it is intended to provide information as to the components inspected.