Loading...
HomeMy WebLinkAboutTerracon - 11/19/2018 (4)POST -TENSION STRESSING REPORT Report Number: 95181011.0547 Irerracon Service Date: 11/14/18 2501 E Loop 820 N Report Date: 11/19/18 Fort Worth, TX 76118-6978 817-268-8600 Reg No: F-3272 Client Project Coury Hospitality Grapevine Main Phase 1 Attn: Mark Brooks 815 South Main Street 7134 S Yale, Ste 400 Grapevine, TX 76051 Tulsa, OK 74136 Proiect Number: 95181011 On this date, a representative of Terracon arrived at the above referenced jobsite as scheduled to observe Post Tension Stressing Operations on Level 5 Upturn Beams & Level 3, Pour 9 & 10. Please note that tendons highlighted in yellow are outside of the tolerance of +/-7%. See attached sheets for recorded data. Services: Terracon Rep.: Adam Wood Reported To: David Saiter w/ Manhattan Contractor: Manhattan Report Distribution: See attached distribution list. Reviewed By: �,Tuipa Senior Project Manager The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. sC0001, 10-16-13, Rev.10 Page 1 of 1 MEASURED ELONGATION CALC TENDON ELONG MARK (in.) End 1 End 2 (in.) (in.) -7% Total Recorded (in.) Restress (psi or 7% kips) TOTAL (in.) % (+/-) REMARKS M022A 13 15.375 12.09 15.38 13.91 15.375 18% M022B 13 14.75 12.09 14.75 13.91 14.75 13% M022C 13 14.75 12.09 14.75 13.91 14.75 13% M022D 13 14.875 12.09 14.88 13.91 14.875 14% M022E 13 14.875 12.09 14.88 13.91 14.875 14% M022F 13 14.25 12.09 14.25 13.91 14.25 10% M 107A 1.75 2 1.63 2.00 1.87 2 14% M107B 1.75 2 1.63 2.00 1.87 2 14% M107C 1.75 2 1.63 2.00 1.87 2 14% M107D 1.75 1.875 1.63 1.88 1.87 1.875 7% M107E 1.75 1.75 1.63 1.75 1.87 1.75 0% M107F 1.75 1.875 1.63 1.88 1.87 1.875 7% M107G 1.75 2.25 1.63 2.25 1.87 2.25 29% U253 3.625 3.5 3.37 3.50 3.88 3.5 -3% U089 7.5 0.00 7.50 0.00 7.5 #DIV/0! No Elongation U090A 6.875 0.00 6.88 0.00 6.875 #DIV/0! No Elongation U090B 7 0.00 7.00 0.00 7 #DIV/0! No Elongation U254 3.625 3.375 3.37 3.38 3.88 3.375 -7% U091A 7.125 0.00 7.13 0.00 7.125 #DIV/0! No Elongation U091B 6.75 0.00 6.75 0.00 6.75 #DIV/0! No Elongation U092 7 0.00 7.00 0.00 7 #DIV/0! No Elongation U255 3.625 3.5 3.37 3.50 3.88 3.5 -3% U093A 3.5 0.00 3.50 0.00 3.5 #DIV/0! No Elongation U093B 3.875 0.00 3.88 0.00 3.875 #DIV/0! No Elongation U094A 8.75 0.00 8.75 0.00 8.75 #DIV/0! No Elongation U094B 7.625 0.00 7.63 0.00 7.625 #DIV/0! No Elongation U261 7.25 0.00 7.25 0.00 7.25 #DIV/0! No Elongation U105 3.625 4.25 3.37 4.25 3.88 4.25 17% Broken Calculation elongations didn't match on several cables due to the previous issues. Due to U261 & U105 measurements there is potential they were flipped during the pre -pour. After the concrete broke @ dead end it appears U261 is indeed the outside cable. U089, U090A, U0906, U091A, U09113, U092, U093A, U09313, U094A, and U094B were pulled with no calculated elongations as fixes for Level 3 pour 9 & 10. SHEETTITLE: ELONGATION RECORDS Jack#1: MR567 JOB/LOCATION: Grapevine Main Phase I Jack#2: CONTRACTOR: Manhattan Jack #1 PSI: 7000 LEVEL/POUR: Level 5, Upturn Beams & Level 3, Pour 9 & 10 Jack #1 PSI: DATE: 11/14/18 1 STRESS BY: K & A Rebar VERIFIED BY: Adam Wood PAGE 1 OF 1 Distribution Paae Report Number: 95181011.0547 Service Date: 11/14/18 Report Date: 11/19/18 Task: Distribution List (1) Coury Hospitality, Mark Brooks (1) AECC Inc, Lee Ledet (1) ArchiTexas, Michael Karnowski (1) City of Grapevine TX, Curtis A Bergthold (1) City of Grapevine TX, Hans Strayer (1) City of Grapevine TX, Paul M Lee (1) City of Grapevine TX, Scott Williams (1) City of Grapevine TX, sbatte@grapevinetexas.gov (1) JQ Engineering, Mike Oler (1) Manhattan Construction Company, Ben Jensen (1) Manhattan Construction Company, Chase Pritchard (1) Manhattan Construction Company, Daniel Rideau (1) Manhattan Construction Company, David Saiter (1) Manhattan Construction Company, Frederick Moore (1) Manhattan Construction Company, Klint Robertson (1) Manhattan Construction Company, Matthew Powell (1) Manhattan Construction Company, Robert Montgomery (1) Walker Consultants, Martha M. Villanueva Irerracon 2501 E Loop 820 N Fort Worth, TX 76118-6978 817-268-8600