HomeMy WebLinkAboutAlpha Testing - 1/7/2019X
PT Drawings X
Proper Cover
Proper Support
X
X
X
Stirrup Size
X
X
X
Cable/Tendon Count &
Spacing
Respectfully Submitted,
Geotechnical Engineering | Construction Materials Testing | Environmental Engineering
•
approval. Test results and reports apply only to the samples tested and/or observed, and are not indicative of the qualities of apparently identical or similar specimens. Technician time is from portal to portal. MF-019(8/2/2016)
Our test results and reports are for the exclusive use of the Client (and designated recipients) and shall not be reproduced and/or distributed except with express approval of ALPHA. The use of our name and test results must receive our written
Size of Reinforcement
Correct Splicing
Based on the representative's visual observation using the provided project plans, the area
Bar Length & Spacing
Proper Placement
Reinforcement Tied Properly
X
Wall 11: Missing shear key - Corrected; A19Wall 13: Form was not placed correctly- corrected
Number of Reinforcement
Remarks:
was compliant
Grade Beam / Column Size
X
SheathingCable/Tendon Drape
Wall 10
Wall 11
Wall 13
Observation Information
X
X
X
X
Tim Begole Sr.
Project:
Alpha Testing, Inc.
5058 Brush Creek Rd
Fort Worth, TX 76119
www.alphatesting.com
TBPE Firm No. 813
Reinforcing Steel
Observation Report
The representative observed the reinforcing steel related items for the following areas:
An Alpha Testing engineering representative traveled to the above referenced project to perform a reinforcing steel observation as scheduled.
01/07/2019Service Date:
Grapevine, TX 76051
Client:Grapevine - Colleyville ISD
30510 Ira E Woods Ave
Work Order Number:
Project Number:
Report Date:
Weather:
Mustang Panther Stadium Pkg A & Pkg B
Grapevine, Texas Page Number:
498140
1 of 1
Clear
1/16/2019
F171917
Technician:Guerrero, Victor
The contractor was notified of the observation result and the engineering representative returned to the Fort Worth Office.
Item Observed
9/15/2017
X
Not Correct Item Observed
•
•
N/ACorrectNot Correct
Reinforcement Clean
N/A
•Plan Sheet:
•Main Entrance Stairs Sides / Handrails (between walls 13 and 11)
RW1.14
The representative utilized the following provided project plans to perform the observation:
Form Clean
Dowels in Place
Stirrup Spacing
RW1.16 / RW1.15
•Date:
Detail Sheet:•
Correct
X
X
X
Drawings Approved
Grade Reinforcement
X
X